R.Murugesan, S/O.(Late) P.Ramu v. The Executive Engineer,
BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED: 18.04.2018
CORAM:
THE HONOURABLE MR.JUSTICE M.S.RAMESH W.P.(MD) No.19849 of 2017 and W.M.P.(MD) No.16111 of 2017 R.Murugesan ... Petitioner vs.
1. The Executive Engineer Tamil Nadu Electricity Generation and Distribution Corporation (TANGEDCO) Periyakulam, Theni District
2. The Assistant Engineer Tamil Nadu Electricity Generation and Distribution Corporation (TANGEDCO) East Sub-Division Andipatti, Theni District
3. The Junior Engineer Tamil Nadu Electricity Generation and Distribution Corporation (TANGEDCO) East Sub-Division Andipatti, Theni District
4. Kuyilan ... Respondents [R4 is impleaded vide order dated 18.04.2018 made in W.M.P.
(MD) No.5928 of 2018] PRAYER: Writ Petition filed under Article 226 of the Constitution of India for issuance of a writ of mandamus directing the respondents to re-locate the Electric Transformer installed in Survey No.163/2, Patta No.319 at Kothapatti Village, Andipatti Taluk, Theni District, thereby considering the petitioner's representation, dated 04.10.2017.
For Petitioner :
Mr.V.Sankaranarayanan For Respondents :
Mr.S.M.S.Johnny Basha Standing Counsel for R1 to R3 Mr.J.Senthil Kumaraiah for R4 https://hcservices.ecourts.gov.in/hcservices/
O R D E R
It is the case of the petitioner that the Electric Transformer had been erected by the first respondent herein in his Patta land in Survey No.163/2 at Kothapatti Village, Andipatti Taluk, Theni District. Hence, the present writ petition has been filed seeking for a direction to the respondents 1 to 3 to relocate the Electric Transformer installed in his Patta land.
2. Today, when the matter was called, the learned counsel appearing for the impleaded fourth respondent relied upon the survey report of the Village Administrative Officer, dated 26.10.2017 and submitted the Electric Transformer has been installed only in Survey No.164 and not in Survey No.163/2 as claimed by the petitioner. As such, the petitioner cannot have any grievance with regard to the installation of the Electric Transformer. In view of the same, no further orders are required in the present writ petition.
3. Accordingly, the writ petition stands closed. No costs. Consequently, connected miscellaneous petition is closed. Sd/- Assistant Registrar (CS-I) /True Copy/ Sub Assistant Registrar + 1 CC TO Mr.J.SENTHIL KUMARAIAH, ADVOCATE IN SR No. 62055 KRK TE/SV-MMS/SAR-4 : 09/05/2018 : 2P/2C W.P.(MD) No.19849 of 2017 and W.M.P.(MD) No.16111 of 2017 18.04.2018 https://hcservices.ecourts.gov.in/hcservices/