Paramasivam .S v. The Superintending Engineer
BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT Dated : 04.12.2024
CORAM:
THE HONOURABLE MRS.JUSTICE L.VICTORIA GOWRI S.Paramasivam ... Petitioner Vs.
1.The Superintending Engineer, O/o. the Superintending Engineer, Meenatchinaickenpatti, Dindigul District - 624002.
2.The Executive Engineer, Distribution, TNEB/TANGEDCO, Batlagundu, Dindigul District.
3.The Assistant Executive Engineer, Distribution, TNEB/TANGEDCO, Nilakottai, Dindigul District.
4.The Inspector of Police, Ammainaickanoor Police Station, Dindigul District.
5.M.Mahamuni 6.M.Veeramani 7.M.Sangaiah ... Respondents PRAYER : Writ Petition filed under Article 226 of the Constitution of 1/5
India for issuance of a Writ of Mandamus, directing the respondents 1 to 3 to provide Electricity connection to the petitioner's agricultural irrigation Motor Pump set in Survey No.118/3, 118/4, situated at Kattakoothanpatti Village, Nilakottai Taluk, Dindigul District, with adequate protection of respondent no.4.
For Petitioner : Mr.I.Pinaygash For Respondents 1 to 3 : Mr.S.Deenadhayalan Standing Counsel For 4th Respondent : Mr.K.Gnanasekaran Government Advocate (Crl.) For Respondents 5 to 7 : Mr.C.V.K.M.Gopinath
ORDER
This Writ Petition is filed, seeking to direct the respondents 1 to 3 to provide Electricity connection to the petitioner's agricultural irrigation Motor Pump set in Survey No.118/3, 118/4, situated at Kattakoothanpatti Village, Nilakottai Taluk, Dindigul District, with adequate protection of respondent no.4.
2.Heard the learned counsels on either side and carefully perused the entire materials available on record.
3.When the matter was called up for hearing, the learned Standing Counsel appearing for the respondents 1 to 3 submitted that the said exercise could not be completed only because of the objection raised by the respondents 5, 6 and 7. However, work would be conducted on erection of one more electric pole.
2/5
4.In view of the above, this Court hereby direct the fourth respondent to give adequate police protection to the respondents 1 to 3 to complete the process of giving electricity connection to the petitioner's agricultural purpose in Survey No.118/3, 118/4, situated at Kattakoothanpatti Village, Nilakottai Taluk, Dindigul District, within a period of four weeks from the date of receipt of copy of this order. 5.Accordingly, this Writ Petition is disposed of. There shall be no order as to costs.
04.12.2024 NCC : Yes / No Index :
Yes / No Internet :
Yes Mrn 3/5
To 1.The Superintending Engineer, O/o. the Superintending Engineer, Meenatchinaickenpatti, Dindigul District - 624002.
2.The Executive Engineer, Distribution, TNEB/TANGEDCO, Batlagundu, Dindigul District.
3.The Assistant Executive Engineer, Distribution, TNEB/TANGEDCO, Nilakottai, Dindigul District.
4.The Inspector of Police, Ammainaickanoor Police Station, Dindigul District.
4/5
L.VICTORIA GOWRI, J.
Mrn 04.12.2024 5/5