BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED: 12.11.2025

CORAM:

THE HON'BLE MS.JUSTICE P.T.ASHA W.P.(MD).No.15849 of 2025 and W.M.P(MD)Nos.11988, 11989 and 15751 of 2025

1. K.Sakthivel

2. P.Subramanian

3. S.P.Rajendran Petitioners 1 to 3 are represented by their power agent M.Raja Mohammed, S/oMohammed Younis, No.20/588, Vedachalapuram, Thogaimalai, Kulithalai Taluk, Karur District.

... Petitioners Vs.

1. The District Collector, Karur District, Collectorate, Karur.

2. The Chief Engineer, Non-Conventional Energy Source, TANGEDCO, Anna Salai, Chennai.

3. The Superintending Engineer, Karur Electricity Distribution Circle, Karur - 639 002.

1/6

4. The Executive Engineer, Operation and Maintenance, Kulithalai, Karur District.

5. The Assistant Executive Engineer, Kulithalai, Karur District.,

6. The President, Porundhalur Panchayath, Kulithalai Taluk, Karur District.

7. M/s. Senkarvel Proserve Pvt. Ltd., No.79, Athulapayam Road, Somanur, Coimbatore.

8. A.Shajahan

9. M.Alavudeen

10. M.I.Rahamathullah

11. S.Mohamed Ibrahim

12. S.Abdul Rajak

13. K.Sethu (R8 to R13 are impleaded vide court order dated 09.07.25 in WMP(MD)No.14261/25 in WP(MD)No.15849/25 by CSNJ) 2/6

Prayer: Writ Petition filed under Article 226 of the Constitution of India, praying this Court to issue a Mandamus forbearing the respondents 2 to 5 from erecting high tension electricity lines and supply high voltage electricity in the residential area in survey no.435/2B, 436/2H ad 436/3 in Porundhalur Village, Kulithalai Taluk, Karur District and pass such further or other orders as this Honble court may deem fit and proper in the circumstances of this case and thus render justice. For Petitioner : Mr.K.S.Kathiravan For R2 to R5 : Mrs.D.Farjana Ghoushia Special Government Pleader For R6 : Mr.B.Ramanathan Additional Government Pleader For R7 : Mr.J.Barathan for Mr.B.Anandan For R8 to R13 : Mrs.Porkodi Kannan M/s.Polax Legal Solution

ORDER

The above writ petition has been filed for the following relief:- "Writ Petition filed under Article 226 of the Constitution of India, praying this Court to issue a Mandamus forbearing the respondents 2 to 5 from erecting high tension electricity lines and supply high voltage electricity in the residential area in survey no. 435/2B, 436/2H ad 436/3 in Porundhalur Village, Kulithalai Taluk, Karur District and pass such further or other orders as this Honble court may deem fit and proper in the circumstances of this case and thus render justice."

3/6

2. When the matter is taken up for hearing today, the learned counsel appearing for the 7th respondent has filed an affidavit, wherein it has been stated as follows:- "5. I submit that, I undertake on behalf of my company that: (a)The construction activities will not endanger or affect the life, property, or livelihood of he petitioners or the public; (b)We undertake to add a protective cover over the existing condutor on the side passing adjacent to the petitioners plot boundaries in the layout;

(c) The line will be energized only after inspection and approval by the competent authority from TNGECL; (d)The company will coordinate with the TANGEDCO/TNGECL officials throught the process to ensure full compliance;

(e) This undertaking is given voluntarily and in good faith to assure this Hon'ble Court that the interests of the petitioners and all residents will be protected. We are committed to completing the project lawfully, safely and transparently." 4/6

3. On the basis of the above undertaking, the writ petition stands disposed of with a direction to the respondents 2 to 5 to ensure that the electricity lines do not enter into the petitioner's property. The affidavit filed by the 7th respondent will be treated as part and parcel of this order.

4. The writ petition stands disposed of with the above observations. No costs. Consequently, connected miscellaneous petitions are closed. 12.11.2025 NCC :yes/No Index :yes/No Internet:yes/No rgm P.T.ASHA, J.

rgm 5/6

To

1. The District Collector, Karur District, Collectorate, Karur.

2. The Chief Engineer, Non-Conventional Energy Source, TANGEDCO, Anna Salai, Chennai.

3. The Superintending Engineer, Karur Electricity Distribution Circle, Karur - 639 002.

4. The Executive Engineer, Operation and Maintenance, Kulithalai, Karur District.

5. The Assistant Executive Engineer, Kulithalai, Karur District.,

6. The President, Porundhalur Panchayath, Kulithalai Taluk, Karur District.

W.P.(MD).No.15849 of 2025 and W.M.P(MD)Nos.11988, 11989 and 15751 of 2025 12.11.2025 6/6