BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT Dated : 20.07.2017 CORAM :

THE HONOURABLE MR.JUSTICE K.K.SASIDHARAN AND THE HONOURABLE MR.JUSTICE G.R.SWAMINATHAN W.P(MD)No.7937 of 2017 and W.M.P(MD).No.6154 of 2017 and 10023 of 2017 A.Velmurugan ... Petitioner Vs.

1. The District Collector, Tirunelveli District, Tirunelveli.

2. The Tahsildar, Nanguneri Taluk, Tirunelveli District.

3. A.Maria James, Secretary, Rural Uplift Centre, Nanguneri, Tirunelveli District.

... Respondents Prayer : Petition filed under Article 226 of the Constitution of India, praying for issuance of a Writ of Mandamus, to direct the respondents No.1 and 2 to prevent the illegal construction carry out by the third respondent in Survey No.1032, Thalapathisamuthiram Part - I, Nanguneri Taluk, Tirunelveli District for an extent of 0.47.0 Hectares vide Peace Committee Meeting held on 04.01.2017.

For Petitioner : Mr.P.Banuprasath For Respondents : Mr.M.Govindan, Spl. Govt. Pleader for RR1 & 2 Mr.K.Vamanan for R3 Mr.M.K.Malaichamy for proposed impleading party.

O R D E R

(Order of the Court was made by K.K.SASIDHARAN, J.) The petitioner filed this writ petition to direct the respondents 1 and 2 to prevent the third respondent from putting up illegal construction by encroaching upon the land in Survey No.1032, Thalapathisamuthiram Part - I, Nanguneri Taluk, Tirunelveli District.

https://hcservices.ecourts.gov.in/hcservices/

2.The learned counsel for the third respondent submitted that the panchayat has taken a decision to allot the land in question to the third respondent for construction of a Creche. 3.Though the third respondent has taken up a contention that a decision was taken by the panchayat to allot the land in question to her, there is nothing on record to show the allotment of land. We, therefore direct the second respondent to consider the representation submitted by the petitioner dated 16 December 2016, on merits and as per law after issuing notice to the third respondent. In case, it is made out that there is no permission given by the Government to the third respondent to put up a building in Government land, appropriate follow up action should be taken by the second respondent. Such exercise shall be completed within four months from the date of receipt of a copy of this order. There shall be a further direction to the third respondent not to put up further constriction till the disposal of the matter by the second respondent.

4.The writ petition is disposed of with the above direction. No costs. Consequently, connected miscellaneous petitions are closed.

Sd/- Assistant Registrar(CS-II) /True Copy/ Sub Assistant Registrar To

1. The District Collector, Tirunelveli District, Tirunelveli.

2. The Tahsildar, Nanguneri Taluk, Tirunelveli District.

+1cc to Mr.P.Banuprasath, Advocate Sr.No.66727 +1cc to Mr.K.Vamanan, Advocate Sr.No.67236 +1cc to Spl.Government Pleader Sr.No.67005 SKM/ARUL VB/KK/SAR4/17/08/2017/2P/6C W.P(MD)No.7937 of 2017 and W.M.P(MD).No.6154 of 2017 20.07.2017 https://hcservices.ecourts.gov.in/hcservices/