P.Murthyraajan v. State Of Tamilnadu Represented
BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED : 27.04.2017
CORAM
THE HONOURABLE MR.JUSTICE S.S.SUNDAR W.P.(MD).No.8284 of 2017 and W.M.P.(MD) No.6343 of 2017 P.Murthyraajan,
...Petitioner
Vs.
1. State of Tamilnadu represented by Secretary to Government, Public Works Department, Fort St.George, Chennai.
2. The Engineer in Chief (Water Resources Department) & Chief Engineer (General), Public Works Department, Chepauk, Chennai.
...Respondents
PRAYER: Writ petition filed under Article 226 of the Constitution of India, praying to issue a Writ of Mandamus, directing the 1st respondent include the petitioner's name in the existing promotion panel (2016-17), for the post of Executive Engineers (Civil), as per his seniority, by disposing his representation dated 11.02.2017.
For Petitioner :Mr. R.Suriyanarayanan For Respondents :Mr. N.S.Karthikeyan Additional Government Pleader
O R D E R
This Writ petition has been filed by the petitioner for issuance of a Writ of Mandamus, directing the first respondent include the petitioner's name in the existing promotion panel (2016-17), for the post of Executive Engineers (Civil), as per his seniority, by disposing his representation dated 11.02.2017. 2.The learned counsel for the petitioner would submit that the petitioner would be satisfied, if a direction is issued to the first respondent to consider his representation dated 11.02.2017, within a time frame stipulated by this Court. https://hcservices.ecourts.gov.in/hcservices/
3.Having regard to the limited scope of the prayer now sought for before this Court, by the learned counsel for the petitioner, without expressing any opinion on the merits of the petitioner's case, this Court is inclined to pass the following direction:
"The first respondent is directed to consider the petitioner's representation 11.02.2017, and pass appropriate order in accordance with law, within a period of eight weeks from the date of receipt of a copy of this order."
4. With the above direction, this Writ Petition is disposed of. No costs. Consequently, the connected W.M.P(MD) No.6343 of 2017 is closed.
Sd/- Assistant Registrar(Records) /True Copy/ Sub Assistant Registrar To
1. Secretary to Government, State of Tamilnadu, Public Works Department, Fort St.George, Chennai.
2. The Engineer in Chief (Water Resources Department) & Chief Engineer (General), Public Works Department, Chepauk, Chennai.
+1cc to M/S. R.SURIYA NARAYANAN, Advocate, SR.No.84485 W.P.(MD).No.8284 of 2017 and W.M.P.(MD) No.6343 of 2017 27.04.2017 SDS/SV/MMS/SAR 3/16.05.2017/2P/4C https://hcservices.ecourts.gov.in/hcservices/