Madras High CourtCMP(MD)/9759/2025ordered

M/S.Nlc Tamil Nadu Power Ltd v. M/S.Tecton Engineering And Construction L.L.C

2025-06-27Honourable Mr Justice M.Dhandapani4 pages

BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT Civil Appellate Jurisdiction Friday, the Twenty Seventh day of June Two Thousand and Twenty Five PRESENT THE HONOURABLE MR. JUSTICE M.DHANDAPANI IN CRP(MD).NO.1393 OF 2024 M/s.NLC Tamil Nadu Power Ltd Represented by its Executive Director Planning and Contracts Neyveli House 135 Periyar EvR Road Kilpauk Chennai - 600 010 and also at Chief Executive Officer, NLC Tamilnadu Power Limited Harbour Estate, Tuticorin 628 004 ... Petitioner/Petitioner/Revision Petitioner Vs 1 M/s.Tecton Engineering and Construction L.L.C Represented by its Authorised Representative Samuel Raj Gnanalah, 2 Bank of Baroda Through its Chief Manager Mount Road Branch, 150 A PB No.2246 Mount Road,Chennai 600 002.

... Respondents/Respondents/Respondents 1/4

Prayer in CMP(MD).No.9759 of 2024:- Civil Miscellaneous Petition is filed under Section 151 of CPC, Extending the bank guarantees of Rs.13,52,70,609/- and USD 150,879/- till the final disposal of the Arbitration OP under AR.OP.No.149/2024 on the file of the Learned Principal District Judge, Tuticorin.

Prayer in CRP(MD) No.1393 of 2024 :- Civil Revision Petition is filed under Article 227 of the constitution of India, to set aside the order of notice passed in I.A No.2 of 2024 in AR OP No.149 of 2024 on the file of Principal District Judge, Tutucorin dated 26.06.2024. ORDER:- This Civil Miscellaneous Petition coming on for orders on this day and upon perusing the petition and the affidavit filed in support thereof and upon hearing the arguments of M/s.K.R.Laxman, Advocate for the Petitioner and of M/s.P.J.Rishikesh for R1, this Court made the following order: The petitioner is the Neyveli Lignite Corporation and they filed the Civil Revision Petition to set aside the order in IA No.2/2024 in Arbitration OP No.149/2024 dated 10.07.2024. This petition is filed to extend the bank guarantee already granted till the disposal of the arbitration proceedings.

2. This Court vide order dated 20.09.2024 directed the Principal District Judge, Tuticorin to take up the Arbitration OP and dispose the same on or before 30.11.2024 2/4

and issued a direction to keep the bank guarantee alive till 15.12.2024 and the said period was subsequently extended. However, till date the Arbitration OP has not been disposed of and the concerned Court has not sought for any extension before this Court.

3. Considering the said submission, the Principal District Judge, Tuticorin is directed to dispose of the arbitration proceedings in Arbitration OP No.149/2024 on or before 25.08.2025 and the bank guarantee is extended up to 10.09.2025. Sd/- Assistant Registrar ( C.O ) // True Copy // / /2025 Sub Assistant Registrar ( CS-I / II / III / IV ) TO 1.The Principal District Judge, Tutucorin.

Copy to 1.The Section Officer, Judicial Section, Madurai Bench of Madras High Court, Madurai 3/4

ORDER DATED : 27/06/2025 ==========================

ORDER

========================== IN CRP(MD). NO.1393 OF 2024.

Giving direction and etc.

as stated within.