Rani E v. The Managing Director
BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED : 19.06.2026
CORAM:
THE HONOURABLE MR.JUSTICE MUMMINENI SUDHEER KUMAR E.Rani ... Petitioner -vs1.The Managing Director Tamil Nadu State Transport Corporation (Kum) Limited TNSTC Head Office No.27, Railway Station New Road Kumbakonam-612 001 2.The Administrator Tamil Nadu State Transport Corporation Pension Fund Trust Thiruvalluvar Illam Pallavan Salai, Chennai-02 3.The General Manager Tamil Nadu State Transport Corporation (Kum) Limited Karaikudi Region Maruthupathi, Managiri Karaikudi, Sivagangai District ... Respondents
PRAYER: Petition filed under Article 226 of the Constitution of India, to issue a writ of mandamus directing the respondents to revise the petitioner's husband's retirement benefits as per the wage settlement made under Section 12(3) of the I.D.Act dated 04.01.2018 and consequently directing the respondents to revise and re-fix his retirement benefits and to disburse difference amounts in his monthly pension, commuted value of pension, gratuity, earned leave salary with interest the rate of 6% per annum payable from 01.09.2016 to till date of actual payment by considering the petitioner's representation dated 12.03.2026.
For Petitioner :
Mr.SP.Vijaynivas For Respondents :
Mr.P.F.Ferlin Castro Standing Counsel for R1 & R3 Mr.S.C.Herold Singh Standing Counsel for R2
O R D E R
Mr.P.F.Ferlin Castro, learned Standing Counsel, takes notice for the respondents 1 & 3 and Mr.S.C.Herold Singh, learned Standing Counsel, takes notice for the second respondent.
2. With the consent of both sides, this writ petition is disposed of at the admission stage.
3. Heard the learned counsel for the petitioner and the learned Standing Counsels appearing for the respective respondents.
4. This writ petition has been filed for a mandamus directing the respondents to revise the retirement benefits payable to the petitioner's husband as per the wage settlement made under Section 12(3) of the I.D.Act dated 04.01.2018 and consequently directing the respondents to revise and re-fix his retirement benefits and to disburse difference amounts of the monthly pension, commuted value of pension, gratuity, earned leave salary with interest the rate of 6% per annum payable from 01.09.2016 to till date of actual payment by considering the petitioner's representation dated 12.03.2026.
5. Today, when the matter is taken up for consideration, learned counsel on either side agree that the issue that arises for consideration in this writ petition is squarely covered by an order passed by the Coordinate Bench of this Court in W.P.(MD) No.3191 of 2026, dated 05.02.2026, in an identical fact situation and a copy of the said order is also placed before this Court. The said order specifically deals with the 15th Wage Settlement and whereas, the case on hand is in respect of the Wage Settlement dated 04.01.2018.
6. In the light of the consensus, this Court does not see any reason to adjudicate the case on hand on merits and is of the view that this writ petition can be disposed of in terms of the said order dated 05.02.2026, passed by the Coordinate Bench of this Court in W.P.(MD) No.3191 of 2026, wherein, the learned Single Judge has held as follows: "7.The petitioner's husband was in service as a permanent employee of the Transport Corporation as on 01.09.2023 and therefore, he is entitled for the benefits as per this 15th wage settlement. The petitioner's husband died, while he was in service on 27.12.2023 and he was paid with the retirement benefits as per the earlier wage settlement. The 15th wage settlement provides revision of scale of pay by 6% on the basic pay, for those who were in service as on 01.09.2023, however monetary benefits with effect from 01.09.2024. Therefore, the petitioner's husband is entitled for the monetary benefits, pursuant to the revision of scale of pay from 01.09.2024 and the consequential retirement benefits.
8.Admittedly, such a revision has not been made till date. Any belated settlement of monetary benefits due to an employee needs to be settled with interest at the rate of 6% per annum. Therefore, this writ petition stands allowed with a direction to the respondent Transport Corporation to revise the pay scale of the petitioner's
husband with effect from 01.09.2023 and provide the monetary benefits with effect from 01.09.2024, as per the 15th wage settlement dated 29.05.2025 and settle the benefits along with arrears to the petitioner within a period of six months from the date of receipt of a copy of this order, with interest @ 6% per annum. The interest shall be calculated for the period beyond Clause 37(b) of the settlement dated 29.05.2025 till the date of actual payment. There shall be no order as to costs."
7. In the light of the above, this writ petition is allowed directing the respondents to revise the pay scale of the petitioner's husband with effect from 04.01.2018 and provide all the consequential monetary benefits as per the Wage Settlement dated 04.01.2018 and settle all other benefits in terms of the said Settlement and pay arrears thereon to the petitioner, within a period of five months from the date of receipt of a copy of this order, together with interest at the rate of 6% per annum for the belated payment. No costs. 19.06.2026 NCC :
Yes / No Index :
Yes / No Internet :
Yes / No krk
MUMMINENI SUDHEER KUMAR, J.
krk 19.06.2026