BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED: 07.11.2022

CORAM:

THE HONOURABLE MRS.JUSTICE V.BHAVANI SUBBAROYAN in W.P(MD)No.13996 of 2021 VE.Muthiah @ Natarajan ... Petitioner Vs.

1.T.Ramar, The Secretary, R.No.786, Tiruchirappalli Co-operative House Construction Society Ltd., Door No.33, Community Centre, M.S.Manian Salai, Thillai Nagar Main Road, Thillai Nagar, Tiruchirappalli District - 620 018.

2.Roach Sekar, The Co-operative Sub-Registrar/Administrator, R.No.786, Tiruchirappalli Co-operative House Construction Society Ltd., Door No.33, Community Centre, M.S.Manian Salai, Thillai Nagar, Main Road, Thillai Nagar, Tiruchirappalli District - 620 018.

... Respondents 1/4

Prayer:- Contempt Petition is filed under Section 11 of Contempt of Courts Act, praying to punish the contemnors/respondents for disobeying the order of this Court, dated 11.08.2021, passed in W.P.(MD)No.13996 of 2021. For Petitioner : Mr.S.Karthikeyan For Respondents : Mr.R.Ragavendran Government Advocate

ORDER

Alleging that the order of this Court in W.P.(MD)No.13996 of 2021, dated 11.08.2021, has not been complied with, the petitioner has come up before this Court with this Contempt Petition. 2.

Today, when the matter was taken up for hearing, the learned Government Advocate appearing for the respondents submitted that there is no willful default on the part of the respondents in complying with the order dated 11.08.2021, made in W.P.(MD)No.13996 of 2021, as certain facts were not brought to the knowledge of the respondents and therefore, the delay has occurred in disposing the representation of the petitioner, dated 17.04.2021. After conducting enquiry, providing reasonable opportunity to all the persons 2/4

concerned, final orders shall be passed by the respondents within a period of 16 weeks from today.

3.

Recording the aforesaid submission, this Contempt Petition is closed.

07.11.2022 Index : Yes / No smn2 To 1.T.Ramar, The Secretary, R.No.786, Tiruchirappalli Co-operative House Construction Society Ltd., Door No.33, Community Centre, M.S.Manian Salai, Thillai Nagar Main Road, Thillai Nagar, Tiruchirappalli District - 620 018.

2.Roach Sekar, The Co-operative Sub-Registrar/Administrator, R.No.786, Tiruchirappalli Co-operative House Construction Society Ltd., Door No.33, Community Centre, M.S.Manian Salai, Thillai Nagar, Main Road, Thillai Nagar, Tiruchirappalli District - 620 018.

3/4

V.BHAVANI SUBBAROYAN, J.

smn2 07.11.2022 4/4