Jeyakani.S v. The District Collector
BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED : 01.09.2022
CORAM
THE HONOURABLE MR.JUSTICE G.R.SWAMINATHAN W.P(MD)No.20624 of 2022 and W.M.P.(MD)No.14946 of 2022 S.Jeyakani ... Petitioner Vs.
1.The District Collector, Tuticorin District, Tuticorin.
2.The Superintending Engineer, TANGEDCO, Tuticorin District, Tuticorin.
3.The Executive Engineer, TANGEDCO, Tiruchendur, Tuticorin District.
4.The Assistant Engineer, TANGEDCO, Transmission line from Udankudi Thermal Power Plant to Oddapidaram Sub Station, Thiruchendur, Tuticorin District.
... Respondents Prayer : Writ Petition filed under Article 226 of the Constitution of India, praying this Court to issue a Writ of Mandamus, to direct the 1st respondent to 1/4
consider the petitioners objection before the proceedings to erect High Tension Line through the petitioners land in S.No.622/2B, to an extent of 6 acres 82 cents, situated at Manaduthandupathu, Udankudi village, Tiruchendur Taluk, Tuticorin District based on the petitioner's representation dated 20.08.2022. For Petitioner : Mr.G.Mohan Kumar For R1 : Mr.M.Prakash Additional Government Pleader For R2 to R4 : Mr.S.Dheenadhayalan
ORDER
Heard the learned counsel on either side.
2. All that the petitioner wants is consideration of the petition mentioned representation.
3. The second respondent is directed to enquire into the petition mentioned representation and dispose of the same on merits and in accordance with law after hearing the petitioner within a period of four weeks from the date of receipt of a copy of this order. I make it clear that I have not gone into the merits of the matter. It is for the second respondent to pass order one way or other.
2/4
4. The Writ Petition is disposed of. No costs. Consequently, connected miscellaneous petition is closed.
01.09.2022 Index : Yes / No Internet : Yes/ No rmi Note: Issue Order Copy on 02.09.2022 To The District Collector, Tuticorin District, Tuticorin.
3/4
G.R.SWAMINATHAN, J.
rmi 01.09.2022 4/4