BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED : 23.09.2022

CORAM

THE HONOURABLE Mrs.JUSTICE V.BHAVANI SUBBAROYAN Writ Petition (MD) No.22447 of 2022 M.Govindarajan, S/o.Marimuthu Solagar .. Petitioner

Versus

1.The Assistant Engineer, Minnagar Branch, 2.The Assistant Executive Engineer (Town), 3.The Executive Engineer, 4.The Superintending Engineer, Thanjavur Electricity Distribution Circle, .. Respondents Prayer :- Petition filed under Article 226 of the Constitution of India praying for issuance of a Writ of Mandamus, to direct the respondents to shift the 1/6

petitioner's electricity service connection No.18 to another property of the petitioner at Innathukanpatti in Survey No.261/1, on the basis of the petitioner's representation, dated 29.07.2022, within a stipulated period to be fixed by this Court.

For Petitioner :

Ms.G.Innisai For Respondents :

Mr.S.Deenadhayalan Standing Counsel

ORDER

The petitioner has prayed for issuance of a Writ of Mandamus, directing the respondents to shift his electricity service connection No.18 to his another property at Innathukanpatti in Survey No.261/1, on the basis of his representation, dated 29.07.2022.

2.Heard Ms.G.Innisai, learned counsel appearing for the petitioner and Mr.S.Deenadhayalan, learned Standing Counsel, who takes notice for the respondents. By consent of learned counsel appearing for the parties, the Writ Petition is taken up for final disposal at the admission stage itself. 3.The case of the petitioner is that he is having properties in S.Nos. 231/1B and 261/1 at Innathukanpatti Panchayat in Thanjavur District. He has electricity service connection No.18 for the agricultural land comprised in S.No.231/1B, for about three decades. Later, the said land was acquired by the Government for extension of prevailing Air Force Station, Thanjavur. An 2/6

award of compensation was passed in his favour, through Award No.22/1995, dated 05.05.1995, by proceedings in R.C.No.135/1991. Now, the petitioner intends to change the above electricity service connection No.18 to his another agricultural land situated in S.No.261/1. The petitioner has also given representations to shift the electricity service connection No.18 to the said land. Finally, he came to know that the electricity service connection stands in another person's name. The petitioner is having all original documents pertaining to the allotment of electricity service connection No.18 in his name. It is a mistake committed by the Office of the respondents by entering a wrong name in the Computer. Finally, the petitioner gave a representation to the respondents on 29.07.2022, enclosing all the relevant documents.

However, the respondents did not take any action to shift the said electricity service connection. Hence, the petitioner has approached this Court by way of filing the present Writ Petition for the relief stated supra. 4.The learned Standing Counsel appearing for the respondents submits that the representation of the petitioner will be considered by the authorities concerned, in accordance with law, within a time frame. 5.

representation of the petitioner, dated 29.07.2022, and pass appropriate orders on merits and in accordance with law after providing an opportunity of hearing to the parties concerned, within a period of four weeks from the date of receipt of a copy of this order.

6.The Writ Petition is disposed of with the above direction. No costs. Index : Yes/No 23.09.2022 To 1.The Assistant Engineer, Minnagar Branch, 2.The Assistant Executive Engineer (Town), 3.The Executive Engineer, 4/6

4.The Superintending Engineer, Thanjavur Electricity Distribution Circle, 5/6

V.BHAVANI SUBBAROYAN, J.

smn2 Order made in W.P.(MD) No.22447 of 2022 23.09.2022 6/6