← Library
Madras High CourtWP(MD)/21143/2021disposed of

Arunbabu S v. The District Collector

2024-03-18Honourable Mr Justice D. Krishnakumar,Honourable Mr Justice R.Vijayakumar7 pages

BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED : 18.03.2024

CORAM:

THE HONOURABLE MR.JUSTICE D.KRISHNAKUMAR and THE HONOURABLE MR.JUSTICE R.VIJAYAKUMAR and W.M.P.(MD) No.17712 of 2021 S.Arunbabu ... Petitioner -vs1.The District Collector / Inspector of Panchayats Tiruchirappalli District Collectorate, Tiruchirappalli 2.The Deputy Director of Town and Country Planning Tiruchy Region Kajamalai Main Road Kajamalai Tiruchirappalli-620 023 3.The Panchayat President Mutharasanallur Village Panchayat Mutharasanallur Post Srirangam Taluk Trichy-620 101

4.The President The Anthanallur Panchayat Union Anthanallur Mutharasanallur Post Srirangam Taluk Trichy-620 101 5.A.Kannan 6.K.Baby 7.G.Subramanian 8.S.Jothi Priyadarshini ... Respondents PRAYER: Petition filed under Article 226 of the Constitution of India, to issue a writ of mandamus directing the respondents 1 to 4 to consider the petitioner's representation dated 06.08.2021 and to inspect the disputed construction carrying on by the respondents 5 to 8 at Plot No.13, Ashtalakshmi Nagar, Kaikudi Street, Mutharasanallur, Srirangam Taluk, Trichy and to stop the unauthorized construction as per the existing provision under Sections 56 and 57 of the Tamil Nadu Town and Country Planning Act, 1971.

For Petitioner :

Mr.P.Thiyagarajan For Respondents :

Mr.N.Satheesh Kumar Additional Government Pleader for R1 & R2 Ms.S.Vinodhini for R3

O R D E R

[Order of the Court was made by D.KRISHNAKUMAR, J.] Prayer in this writ petition is to direct the respondents 1 to 4 to consider the petitioner's representation dated 06.08.2021 and to inspect the disputed construction carrying on by the respondents 5 to 8 at Plot No.13, Ashtalakshmi Nagar, Kaikudi Street, Mutharasanallur, Srirangam Taluk, Trichy and to stop the unauthorized construction as per the existing provision under Sections 56 and 57 of the Tamil Nadu Town and Country Planning Act, 1971.

2. According to the petitioner, he has constructed a house in Plot No.14, Ashtalakshmi Nagar, Kaikudi Street, Mutharasanallur, Srirangam Taluk, Trichy District. The respondents 7 and 8 were originally having Plot No.13, adjacent to the petitioner's plot, and they split up the same sold it to the respondents 5 and 6. The seventh respondent, who is a Building Contractor, started construction in the said Plot No.13 for the respondents 5 and 6, without obtaining necessary building plan approval and permission under Tamil Nadu Panchayat Act and its Building Rules, 1997 as well as Tamil Nadu Combined Development and Building Rules, 2019. While putting

up the construction, they have encroached upon the petitioner's compound wall. Seeking to remove the said unauthorized construction, the petitioner gave a representation to the official respondents on 06.08.2021. However, the official respondents have not taken any action based on the said petitioner's representation. Hence, this writ petition.

3. Learned Additional Government Pleader appearing for the respondents 1 and 2, on instructions, submits that if the construction made by the respondents 5 to 8 is found to be an unauthorized construction, the authority concerned will take necessary action for removal of the same in accordance with law.

4. Considering the limited scope of the prayer sought for by the petitioner, without going into the merits of the matter, we direct the second respondent to consider the petitioner's representation dated 06.08.2021, and pass orders on merits and in accordance with law, after providing due opportunity to the parties concerned, within a period of twelve weeks from the date of receipt of a copy of this order.

5. To be noted, in order to curb the unauthorized constructions, the Government has constituted a High Level Monitoring Committee and issued G.O.(2D) No.15, Municipal Administration and Water Supply (MA.1) Department, dated 01.03.2024. The Monitoring Committee shall monitor the inspection of the unauthorized constructions as per the said Government Order. The second respondent shall file an action taken report before the Monitoring Committee for removal of the unauthorized construction made by the respondents 5 to 8.

6. With the above direction, this writ petition is disposed. No costs. Consequently, connected miscellaneous petition is closed. [D.K.K., J.] [R.V., J.] 18.03.2024 NCC :

Yes / No Index :

Yes / No Internet :

Yes / No krk

To:

1.The District Collector / Inspector of Panchayats, Tiruchirappalli District, Collectorate, Tiruchirappalli.

2.The Deputy Director of Town and Country Planning, Tiruchy Region, Kajamalai Main Road, Kajamalai, Tiruchirappalli-620 023.

D.KRISHNAKUMAR , J.

and R.VIJAYAKUMAR, J.

krk and W.M.P.(MD) No.17712 of 2021 18.03.2024