Mumtaj v. The Chief Engineer
BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED : 11.11.2024
CORAM
THE HONOURABLE MR.JUSTICE K.KUMARESH BABU Mumtaj
...Petitioner
Vs 1.The Chief Engineer, Tamil Nadu Electricity Generation and Distribution Corporation, Trichy Distribution Circle, Trichy.
2.The Superintending Engineer, Tamil Nadu Electricity Generation and Distribution Corporation, Pudukkottai District, Pudukkottai.
3.The Executive Engineer, Operation and Maintenance, Tamil Nadu Electricity Generation and Distribution Corporation, Aranthangi, Pudukkottai District.
... Respondents Prayer: Writ Petition filed under Article 226 of the Constitution of India praying this Court to issue a Writ of Mandamus, directing the third respondent to transfer the electricity connection in the petitioner's name by considering her representation dated 25.08.2015 within a stipulated time fixed by this Court.
1/5
For Petitioner : Mr.C.Jeya Prakash For Respondents : Mr.S.Deenadhayalan Standing Counsel
O R D E R
Heard Mr.C.Jeya Prakash, learned counsel for the petitioner and Mr.S.Deenadhayalan, learned Standing Counsel for the respondents.
2. This Writ Petition has been filed praying for a Mandamus, directing the third respondent to transfer the electricity connection in the petitioner's name by considering her representation dated 25.08.2015.
3. It is the case of the learned counsel for the petitioner inspite of intimation to the petitioner to give details as regards the person in whose name the present electricity connections stands, he had not responded. The learned counsel for the petitioner also placed on record a notice sent by him to the petitioner through registered post dated 03.07.2023. 2/5
4. However, considering the fact that the representation was made by the petitioner to the third respondent as early as on 25.08.2015, the petitioner is directed to give a fresh representation to the third respondent within a period of four weeks from today and if any such representation is made by the petitioner, the third respondent shall consider the representation and pass orders within a period of four weeks thereafter, after issuing notice to the petitioner and other individual concerned.
5. With the above direction, this Writ Petition is disposed of. No costs.
11.11.2024 NCC:yes/no Index:yes/no Internet:yes/no Nsr To:
3/5
1.The Chief Engineer, Tamil Nadu Electricity Generation and Distribution Corporation, Trichy Distribution Circle, Trichy.
2.The Superintending Engineer, Tamil Nadu Electricity Generation and Distribution Corporation, Pudukkottai District, Pudukkottai.
3.The Executive Engineer, Operation and Maintenance, Tamil Nadu Electricity Generation and Distribution Corporation, Aranthangi, Pudukkottai District.
K.KUMARESH BABU , J.
4/5
Nsr 11.11.2024 5/5