BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED: 26.08.2025

CORAM:

THE HONOURABLE MR.JUSTICE C.SARAVANAN LP Textiles, rep. by its Partner L.Raguram.

... Petitioner Vs

1. The Superintendent Engineer, Virudhunagar Distribution Circle, Tamil Nadu Generation and Distribution Corporation Ltd (TANGEDCO), Ramamoorthy Road, Virudhunagar.

2. The Executive Engineer, Tamil Nadu Generation and Distribution Corporation Ltd (TANGEDCO), Rajapalayam Division, Rajapalayam.

3. The Assistant Executive Engineer, Tamil Nadu Generation and Distribution Corporation Ltd (TANGEDCO), Rajapalayam Division, 1/4

Rajapalayam.

... Respondents PRAYER: Writ Petition filed under Article 226 of the Constitution of India for issuance of Writ of Mandamus to direct the first respondent to refund the caution deposit paid for petitioner's company's electricity service connection in HTSC No. 079094620406 and deposit the same in petitioner's company's HDFC Bank Current Account No. 50200071231697, Srivilliputhur Branch, based on the proceedings of the third respondent, dated 21.12.2024, 09.06.2025 as well as based on the representation, dated 20.06.2025 within the time limit that may be stipulated by this Court.

For petitioner : Mr. M.Mohanasundaram For respondents : Mr.S.Deenadhayalan Standing Counsel *****

ORDER

This Writ Petition is taken up for hearing at the time of admission with the consent of the learned counsel for the petitioner and the learned Standing Counsel for the respondents.

2. The learned Standing Counsel for the respondents submits that the petitioner's representation dated 20.06.2025 will be considered by the first 2/4

respondent based on the proceedings of the third respondent on 21.12.2024 and 09.06.2025 within a period of four weeks.

3. Recording the same, this Writ Petition is disposed of by directing the first respondent to consider and dispose of the petitioner's representation dated 20.06.2025 as expeditiously as possible preferably within a period of four (4) weeks from the date of receipt of a copy of this order. No costs. Index : Yes / No 26.08.2025 Internet : Yes / No apd To The Superintendent Engineer, Virudhunagar Distribution Circle, Tamil Nadu Generation and Distribution Corporation Ltd (TANGEDCO), Ramamoorthy Road, Virudhunagar.

3/4

C.SARAVANAN, J.

apd 26.08.2025 4/4