BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED: 08.11.2024

CORAM:

THE HONOURABLE MR.JUSTICE K.KUMARESH BABU and W.M.P.(MD) No.17786 of 2024 N.Ramanujam ... Petitioner /vs./ 1.The Executive Director, Power Grid Corporation of India Ltd., No.4, Tidel Park, 12th Floor, Canal Bank Road, Tharamani, Chennai 600 113.

2.The Executive Directors SRTS.II, Power Grid Corporation of India Ltd., Yelahanka400KV/220KVSUB-Station, Southern Region Telecom Control Centre, Near RTO Driving Test Truck, Singanayanahalli, Yelahanka - Dodaballapur Road, Bangalore 560 064, Karnataka.

1/4

3.The Superintending Engineer, Tamil Nadu Electricity Board, Thoothukudi District.

4.The District Executive Magistrate cum Collector, Collectorate, Thoothukudi, Thoothukudi District.

... Respondents PRAYER: Writ Petition filed under Article 226 of the Constitution of India for issuance of Writ of Mandamus, directing the 4th respondent to consider petitioner representations dated 21.10.2016 and 11.11.2016 following the decision of this Court reported in 2015(1) CWC 566.

For Petitioner : No appearance For R3 : Mr.S.Deenadhayalan Standing Counsel For R4 : Mr.J.K.Jeyaseelan Government Advocate

ORDER

When the matter was taken up for hearing on 06.11.2024, there was no representation on behalf of the petitioner. Hence, the matter was directed to be listed today under the caption 'for dismissal'. However, even today, there is no representation on behalf of the petitioner. Hence, the Writ Petition is dismissed 2/4

for non-prosecution. However, there shall be no order as to costs. Consequently, connected Miscellaneous Petition is closed.

Index : Yes / No 08.11.2024 Internet : Yes / No mm To The District Executive Magistrate cum Collector, Collectorate, Thoothukudi, Thoothukudi District.

3/4

K.KUMARESH BABU, J.

mm 08.11.2024 4/4