Ilangovan S v. The Managing Director
1 W.P.(MD)NO.27173 OF 2022 BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED: 01.12.2022
CORAM
THE HONOURABLE MR.JUSTICE G.R.SWAMINATHAN W.P.(MD)Nos.27173 to 27175 & 27177 of 2022 W.P.(MD)No.27173 of 2022 S.Ilangovan Pudukkottai Region, Pillai Thanneer Panthal, Madurai Main Road, Pudukkottai.
1/6
2 W.P.(MD)NO.27173 OF 2022 W.P.(MD)No.27174 of 2022 T.Marikumar W.P.(MD)No.27175 of 2022 V.Dharmarajan 2/6
3 W.P.(MD)NO.27173 OF 2022 W.P.(MD)No.27177 of 2022 O.Thangaraj 3/6
4 W.P.(MD)NO.27173 OF 2022 (in all W.Ps.) For Petitioners : Mr.K.Gokul For Respondents : Mr.K.Jagadees Balan, Standing Counsel.
* * * C O M M O N O R D E R Heard the learned counsel on either side.
2. The writ petitioners were employed in the respondent Corporation They reached the age of superannuation. Their grievance is that they were not given effect of the wage settlement that was entered into on 04.01.2018. It is not in dispute that the said settlement was notionally given from 01.09.2016. The actual monetary benefit was given for the months from 01.09.2017 to 31.12.2017. Admittedly, the petitioners have to be given differences in wages for the aforesaid four months. Their grievance is that they were not given the said wage difference. 4/6
5 W.P.(MD)NO.27173 OF 2022
3. The respondent management is directed to pay the wage difference to the petitioners for the aforesaid period within twelve weeks from the date of receipt of a copy of this order.
4. These writ petitions stand allowed. No costs. 01.12.2022 Index : Yes / No Internet : Yes/ No PMU To:
Pudukkottai Region, Pillai Thanneer Panthal, Madurai Main Road, Pudukkottai.
3. The General Manager, 5/6
6 W.P.(MD)NO.27173 OF 2022 G.R.SWAMINATHAN,J.
PMU W.P.(MD)Nos.
27173 to 27175 & 27177 of 2022 01.12.2022 6/6