Ochappan M v. The Superintending Engineer
BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED: 10.09.2025
CORAM
THE HON'BLE MR.JUSTICE K.KUMARESH BABU M.Ochappan ... Petitioner Vs.
1.The Superintending Engineer, Dindigul Electricity Distribution Circle, Dindigul.
2.The Executive Engineer, Batlagundu Division, Batlagundu, Dindigul District.
... Respondents PRAYER : Writ Petition filed under Article 226 of the Constitution of India, praying this Court to issue a Writ of Mandamus, directing the respondents to dispose off petitioner's representation, dated 17.06.2025 and to pass such further or other orders as this Court. For Petitioner : Mr.R.Thankasamy For Respondents : Mr.B.Ramanathan Standing Counsel 1/4
ORDER
The learned Counsel appearing for the petitioner would submit that the first respondent had passed an order on 08.09.2025 and therefore, he seeks to withdraw the writ petition with liberty to challenge the said order.
2. Recording the same, this Writ Petition stands dismissed as withdrawn with liberty to the petitioner to challenge the order passed by the first respondent. There shall be no order as to costs. 10.09.2025 NCC :
Yes / No Index :
Yes / No Internet :
Yes BTR To 1.The Superintending Engineer, Dindigul Electricity Distribution Circle, Dindigul.
2/4
2.The Executive Engineer, Batlagundu Division, Batlagundu, Dindigul District.
3/4
K.KUMARESH BABU, J.
BTR Order made in 10.09.2025 4/4