← Library
Madras High CourtWP(MD)/28049/2022allowed

Lakshmi v. The Superintending Engineer

2023-10-03Honourable Mr Justice G.R.Swaminathan5 pages

1 W.P.(MD)NO.28049 OF 2022 BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED: 03.10.2023

CORAM

THE HONOURABLE MR.JUSTICE G.R.SWAMINATHAN W.P.(MD)No.28049 of 2022 Lakshmi ... Petitioner Vs.

1. The Superintending Engineer, Tamil Nadu Generation and Distribution Corporation Ltd., TANGEDCO, Dindigul North Electricity Distribution Circle, Meenatchi Nayakan Patti, Bye Pass Road, Dindigul.

2. The Assistant Engineer, Tamil Nadu Generation and Distribution Corporation Ltd., TANGEDCO, Vadamadurai Post, Vedasandur Taluk, Dindigul District.

3. Indirani ... Respondents Prayer: Writ petition is filed under Article 226 of the Constitution of India, to issue a Writ of Certiorarified Mandamus, calling for the records pertaining to the impugned order passed by the 2nd respondent vide his proceedings in Ka.No. Vu.Mi.Po/E.Pe/Nagar/Va.Mathu/Ko./A.No. 207/22 dated 06.10.2022 and quash the same as illegal and consequently direct the 1st respondent to shift the petitioner's existing electricity service connection bearing No. 34 along with the 1/5

2 W.P.(MD)NO.28049 OF 2022 Electric Pole from the landed property in Survey no. 211/1A1A to her landed property in Survey No. 211/1-C situated at Perumpulli Village, Vedasandur Taluk, Dindigul within a time stipulated by this Court.

For Petitioner : Mr.J.Lawrance For R-1 & R-2 : Mr.S.Deenadhayalan, Standing Counsel.

For R-3 : Mr.N.Anandakumar * * *

O R D E R

Heard both sides.

2. The petitioner was enjoying the petition-mentioned service connection. Since the pole from which the petitioner was drawing electricity was located in the neighbour's land, based on the request of the petitioner it was shifted and supply was also temporarily cut off. After the electric pole was shifted on account of the objection raised by the third respondent, the supply was not restored.

2/5

3 W.P.(MD)NO.28049 OF 2022 3.The second respondent informed the petitioner that objection has been received from the third respondent with regard to the pendency of the partition suit. Challenging the stand of the second respondent, the present writ petition came to be filed.

4. The petitioner is said to be the second wife of the father of the third respondent. The third respondent had filed O.S.No.20 of 2022 on the file of the Sub Court, Vedasandur. The land on which the pole has now been erected is also a part of the suit schedule.

5. The apprehension of the third respondent is that in the event of the petition-mentioned land being allotted to her share, difficulties and complications will arise. I am of the view that this apprehension is not well founded. I make it clear that the rights of the parties will abide by the outcome of the partition suit proceedings. The petitioner through her counsel makes it clear that she will not claim any equity by citing this order. Respondents 1 and 2 are directed to restore the supply of electricity to the petitioner. This would be subject to the 3/5

4 W.P.(MD)NO.28049 OF 2022 outcome of the civil suit. This writ petition stands allowed on these terms. No costs.

03.10.2023 NCC : Yes / No Index : Yes / No Internet : Yes / No PMU To:

1. The Superintending Engineer, Tamil Nadu Generation and Distribution Corporation Ltd., TANGEDCO, Dindigul North Electricity Distribution Circle, Meenatchi Nayakan Patti, Bye Pass Road, Dindigul.

2. The Assistant Engineer, Tamil Nadu Generation and Distribution Corporation Ltd., TANGEDCO, Vadamadurai Post, Vedasandur Taluk, Dindigul District.

4/5

5 W.P.(MD)NO.28049 OF 2022 G.R.SWAMINATHAN,J.

PMU W.P.(MD)No.28049 of 2022 03.10.2023 5/5