P.Krishnan v. The Tahsildar
BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED :23.09.2025
CORAM:
THE HONOURABLE MR JUSTICE SENTHILKUMAR RAMAMOORTHY P.Krishnan ... Petitioner Vs
1. The Tahsildar,
2. The Taluk Surveyor,
3. The Village Administrative Officer, Othai Alangulam, Valayapatti,
4. The Inspector of Police, Perungudi Police Station, ... Respondents PRAYER: Writ Petition filed under Article 226 of the Constitution of India, praying this Court to issue a Writ of Mandamus to direct the second and third respondents to survey the land and to fix the four boundaries and install the boundary stone in the petitioner's property in Patta No.3675 in S.Nos.113/19A2 with extent of 0-0.80 ares (2 cents out of 9 cents) located at T.Arasapatti Village, Kallikudi Taluk, Madurai District based on the online application No.2025/0123/25/019907 dated 1/5
09.09.2025 with necessary police protection at the time of survey the petitioner's land based on the representation dated 22.04.2025. For Petitioner : Mr. S.Sivaprakash For Respondents : Mr.P.Thambidurai Government Advocate for R1 to R3 Mr.S.Prakash Government Advocate (Crl.Side) for R4
O R D E R
By relying on a registered sale deed dated 04.09.2002 bearing document No.4835/2002 and patta No.978, the petitioner had applied for a survey of the land in Survey No.3/18. On the ground that such request was not acted upon within a reasonable time, the present Writ Petition has been filed.
2. Learned Government Advocate accepts notice on behalf of respondents 1 to 3 and learned Government Advocate (Crl. Side) accepts notice on behalf of the fourth respondent. Learned Government Advocate submits that the petitioner's request would be acted upon within a period of twelve (12) weeks from the date of receipt of a copy of this order after putting the relevant adjacent landowners on notice. 2/5
3. In response to a specific question, learned counsel for the petitioner submits that there are no title disputes relating to the relevant land. He, however, submits that the adjacent landowners may be put on notice before the matter is proceeded with.
4. Accordingly, the first and second respondents are directed to initiate action on the petitioner's request for a survey and complete the entire exercise within a period of twelve (12) weeks from the date of receipt of a copy of this order, subject to objections, if any, by relevant adjacent landowners who should be put on notice.
5. This Writ Petition is disposed of on these terms. No costs. NCS : Yes/No 23.09.2025 Index : Yes / No Internet : Yes / No apd To
1. The Tahsildar, 3/5
2. The Taluk Surveyor,
3. The Village Administrative Officer, Othai Alangulam, Valayapatti,
4. The Inspector of Police, Perungudi Police Station, 4/5
SENTHILKUMAR RAMAMOORTHY.,J.
apd ORDER MADE IN 23.09.2025 5/5