D.Nalladurai Charles v. The Chief Engineer /Personal (Fac)
BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED : 30.01.2024
CORAM
THE HONOURABLE MRS.JUSTICE L.VICTORIA GOWRI and W.M.P.(MD)Nos.24312 and 24314 of 2023 D.Nalladurai Charles ... Petitioner Vs.
1.The Chief Engineer / Personal (FAC), TANGEDCO, Administrative Branch, NPKRR Maligai, No.144, Anna Salai, Chennai-2.
2.The Chief Engineer (Distribution), TANGEDCO, Tirunelveli Region, Tirunelveli District.
3.The Superintending Engineer, Tirunelveli Electricity Distribution Circle, TANGEDCO, Tirunelveli District.
1/4
4.V.Thangamurugan, Assistant Executive Engineer (Electrical), Tirunelveli Electricity Distribution Circle, TANGEDCO, Ayikudi, 230 KV Sub-Station, Tenkasi District.
... Respondents Prayer : Writ Petition filed under Article 226 of the Constitution of India, praying this Court to issue a Writ of Certiorari, to call for the records relating to the impugned order of the 1st respondent in CE/P/Chennai: Memo No:068840 / G1 / G1(2) / 2023-1 dated 25.11.2023 and the consequential impugned order of the 2nd respondent in Memo No.012232 /2081 / Adm / A.1 / F.AEE / 2023 dated 25.11.2023, and quash the same.
For Petitioner : Mr.D.Venkatesh For Respondents : M/s.M.Parameswari, Standing Counsel
ORDER
When the writ petition was taken up for hearing, the learned Counsel appearing for the petitioner sought permission of this Court to withdraw the 2/4
writ petition and made an endorsement to that effect. The said submission is recorded.
2.In view of the above said submission, the writ petition is dismissed as withdrawn. No costs. Consequently, connected miscellaneous petitions are closed.
30.01.2024 NCC : Yes / No Index : Yes / No Internet : Yes Sml 3/4
L.VICTORIA GOWRI, J.
Sml 30.01.2024 4/4