C.Selvamani v. The Executive Engineer (Distribution)
BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED: 31.10.2025
CORAM
THE HONOURABLE MS.JUSTICE P.T.ASHA Writ Petition(MD)Nos.30786 of 2025 and W.M.P(MD)Nos.23974 & 23975 of 2025 C.Selvamani ..Petitioner Vs 1.The Executive Engineer, (Distribution), Tamil Nadu Generation and Distribution Corporation Ltd., Thirumangalam, 2.The Assistant Executive Engineer, (Distribution), Tamilnadu Generation and Distribution Corporation Ltd., Kallupatti, Peraiyur Taluk, 3.The Assistant Engineer, (Distribution), Tamilnadu Generation and Distribution Corporation Ltd., Peraiyur, Peraiyur Taluk, Madurai District.
..Respondents Prayer in W.P(MD)No.30868 of 2025: Writ Petition filed under Article 226 of the Constitution of India, praying this Court to issue a Writ of Certiorarified Mandamus, to call for the records pertaining to the impugned order passed by the 1st respondent in Letter No.Umipo/Pagir/Perai/Varu.Pirivu/Po3./A.No./25 dated Nil.08.2025 and quash the same and consequently direct the respondents not to disconnect the electricity connection granted to the petitioner's property situates in 1/4
Door numbers 1/189 and 1/190 plot No.11, Navamaruthi nagar, Opposite to K.R.Arts and Science College, Thambipatti, T.Kallupatti Main Road, For Petitioner : Mr.P.Gunasekaran For Respondent : Mr.S.Deenadhayalan Standing Counsel
ORDER
This writ petition has been filed seeking issuance of a Writ of Certiorarified Mandamus to call for the records relating to the impugned order passed by the first respondent in Letter No.Umipo/Pagir/Perai/Varu.Pirivu/Po3./A.No./25, dated Nil.08.2025, quash the same, and consequently direct the respondents not to disconnect the electricity service connection pertaining to the petitioner's property situated at Door Nos.1/189 and 1/190, Plot No.11, Navamaruthi Nagar, opposite to K.R. Arts and Science College, Thambipatti, T. Kallupatti Main Road, Madurai District.
2. It is informed that the electricity service connection of the petitioner has already been disconnected.
3. It is seen that the impugned order has been passed without affording any prior notice to the petitioner, and the disconnection of the electricity service connection has also been effected without such notice. 2/4
4. Though an appeal remedy is available to the petitioner, this Court, taking note of the above circumstances, directs the respondents to restore the petitioner's electricity service connection within a period of one week from the date of receipt of a copy of this order. It is made clear that the petitioner shall thereafter pursue the appeal remedy available under law.
5. This writ petition is disposed of accordingly. No costs. Consequently, connected miscellaneous petitions are closed. 31.10.2025 NCC : Yes/No Index : Yes/No Internet:Yes skn To 1.The Executive Engineer, (Distribution), Tamil Nadu Generation and Distribution Corporation Ltd., Thirumangalam, 2.The Assistant Executive Engineer, (Distribution), Tamilnadu Generation and Distribution Corporation Ltd., Kallupatti, Peraiyur Taluk, 3.The Assistant Engineer, (Distribution), Tamilnadu Generation and Distribution Corporation Ltd., Peraiyur, Peraiyur Taluk, Madurai District.
3/4
P.T.ASHA, J.
skn Writ Petition(MD)Nos.30786 of 2025 and W.M.P(MD)Nos.23974 & 23975 of 2025 31.10.2025 4/4