← Library
Madras High CourtWP(MD)/34127/2025disposed of

K.Periyasamy v. The Superintending Engineer

2025-11-27Honourable Ms. Justice P.T. Asha4 pages

BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED: 27.11.2025

CORAM:

THE HON'BLE MS.JUSTICE P.T.ASHA W.P.(MD).No.34127 of 2025 K.Periyasamy ... Petitioner Vs.

1. The Superintending Engineer, TANGEDCO, TNEB, K.Pudur, Madurai.

2. The Executive Engineer, TANGEDCO, TNEB, Usilampatti, Madurai.

3. The Assistant Executive Engineer, TANGEDCO, TNEB, Checkanoorani, Madurai.

4. The Assistant Engineer, TANGEDCO, TNEB, Checkanoorani, Madurai.

... Respondents 1/4

Prayer: Writ Petition filed under Article 226 of the Constitution of India, praying this Court to issue a Writ of Mandamus directing the respondents to provide electricity connection to the petitioners temple Arulmigu Sri Veerampatti Kaliamman Temple based upon the application in Application Ref.No.2000517611251391 dated 05.11.2025 and pass such further or other orders as this Honble Court may deem fit and proper in the circumstances of the case and thus render justice. For Petitioner : Mr.T.Dinesh For R1 to R4 : Mr.S.Deenadhayalan Standing Counsel

ORDER

The above writ petition has been filed for the following relief:- "Writ Petition filed under Article 226 of the Constitution of India, praying this Court to issue a Writ of Mandamus directing the respondents to provide electricity connection to the petitioners temple Arulmigu Sri Veerampatti Kaliamman Temple based upon the application in Application Ref.No.2000517611251391 dated 05.11.2025 and pass such further or other orders as this Honble Court may deem fit and proper in the circumstances of the case and thus render justice."

2/4

2. Today when the matter is taken up for hearing, Mr.S.Deenadhaylan, learned Standing Counsel appearing for the respondents 1 to 4 would submit that the respondents have no objection in giving electricity service connection in the name of the petitioner temple and in the name of the Poosari.

3. Recording the same, the writ petition stands disposed of with a direction to the respondents to effect electricity service connection in the name of the petitioner temple within a period of two (2) weeks from the date of receipt of a copy of this order. No costs. 27.11.2025 NCC :yes/No Index :yes/No Internet:yes/No rgm 3/4

P.T.ASHA, J.

rgm To

1. The Superintending Engineer, TANGEDCO, TNEB, K.Pudur, Madurai.

2. The Executive Engineer, TANGEDCO, TNEB, Usilampatti, Madurai.

3. The Assistant Executive Engineer, TANGEDCO, TNEB, Checkanoorani, Madurai.

4. The Assistant Engineer, TANGEDCO, TNEB, Checkanoorani, Madurai.

W.P.(MD).No.34127 of 2025 27.11.2025 4/4