M/S.P.Samiyappa Gounder And Bros v. The Superintending Engineer
BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED : 25.11.2025
CORAM:
THE HONOURABLE MR.JUSTICE C.V.KARTHIKEYAN and THE HONOURABLE MR.JUSTICE R.VIJAYAKUMAR M/s.P.Samiyappa Gounder & Bros., No.41, Majid Street, Kangayam-638 701, Tirupur District, Rep. by its Managing Partner, Mr. P.Samiappa Gounder.
... Petitioner in both C.M.Ps.
-vs1. The Superintending Engineer, PWD, WRO Special Project Circle, Palani-624 601.
2. The Executive Engineer, PWD/WRD, Nanganjiyar Basin Division, Palani, Dindigul District.
... Respondents in both C.M.Ps.
3. The Chief Engineer, WRO/PWD/Pollachi Region, Town Hall, Coimbatore.
... 3rd Respondent in C.M.P.(MD)No.19014/2025
COMMON PRAYER: Petitions filed praying to condone the delay of 230 days in representing the AS SR(MD) Nos.27191 and 27192 of 2025. For Petitioner :
Mr.S.Venkatesh (In both C.M.Ps) For Respondents : Mr.A.Kannan, (In both C.M.Ps) Addl. Govt. Pleader COMMON ORDER (Order of the Court was made by C.V.Karthikeyan, J.) These petitions have been filed to condone the delay of 230 days in representing the above appeal in A.S.(MD)SR.Nos.27191 and 27192 of 2025.
2. For the reasons stated in the affidavits filed in support of these petitions, the delay in representation is condoned and the petitions are ordered.
3. Registry is directed to number the Appeal Suit if it is otherwise in order. The connected civil miscellaneous petitions can be listed, if they are otherwise in order and if they are numbered, on 27.11.2025. [C.V.K., J.] [R.V., J.] vsm 25.11.2025
C.V.KARTHIKEYAN , J.
and R.VIJAYAKUMAR , J.
vsm 25.11.2025