IN THE HIGH COURT OF KERALA AT ERNAKULAM

PRESENT:

THE HONOURABLE MR.JUSTICE THOTTATHIL B.RADHAKRISHNAN & THE HONOURABLE MR. JUSTICE SUNIL THOMAS WEDNESDAY, THE 22ND DAY OF JULY 2015/31ST ASHADHA, 1937 DBP.No. 72 of 2015 () -------------------------------- APPLICANT:

------------------ COCHIN DEVASWOM BOARD, REPRESENTED BY THE SECRETARY, COCHIN DEVASWOM BOARD, THRISSUR.

BY ADV. SRI.KRISHNA MENON, SC, COCHIN DEVASWOM BOARD RESPONDENT(S):

---------------------------- 1.

DEPUTY DIRECTOR, LOCAL FUND AUDIT (C.D.) AUDIT, THRISSUR.

2.

THE SECRETARY, TEMPLE ADVISORY COMMITTEE, SPHADIKAM MAHADEVA TEMPLE, ANNALLUR P.O, PIN-680 731.

R1 BY SRI.A.RENJITH, GOVERNMENT PLEADER THIS DEVASWOM BOARD PETITION HAVING BEEN FINALLY HEARD ON 22-07-2015, THE COURT ON THE SAME DAY PASSED THE FOLLOWING: DG

THOTTATHIL B.RADHAKRISHNAN & SUNIL THOMAS, JJ.

----------------------------------------------------------------- DBP.No.72 of 2015 ------------------------------------------------------------------- Dated this the 22nd day of July, 2015

ORDER

Thottathil B.Radhakrishnan, J.

1.This matter relates to remaking of idol of Sphatikam Mahadeva Temple, providing 24 Kgs. of silver from the stock of the Board.

2.Perused materials and the affidavit. We have seen the report of the learned Ombudsman. Sanction as sought for is granted. The work shall be carried out in terms of the suggestions of the learned Ombudsman and the expenditure incurred shall be subjected to audit. It shall be ensured that the work is carried out in a time bound manner.

DBP ordered accordingly.

Sd/- (THOTTATHIL B.RADHAKRISHNAN, JUDGE) Sd/- (SUNIL THOMAS, JUDGE) //TRUE COPY// P.A TO JUDGE DG