← Library
High Court of KeralaDBP/90/2015disposed of

The Travancore Devaswom Board v. The Deputy Director

2015-08-19Honourable Mr. Justice Sunil Thomas,Honourable Mr.Justice Thottathil B.Radhakrishnan2 pages

IN THE HIGH COURT OF KERALA AT ERNAKULAM

PRESENT:

THE HONOURABLE MR.JUSTICE THOTTATHIL B.RADHAKRISHNAN & THE HONOURABLE MR. JUSTICE SUNIL THOMAS WEDNESDAY, THE 19TH DAY OF AUGUST 2015/28TH SRAVANA, 1937 DBP.No. 90 of 2015 () ---------------------- (IN THE MATTER OF TDB REPORT NO.90 OF 2015 - AWARD OF CONTRACT FOR THE WORK OF CONSTRUCTING OFFICE BUILDING AND VAZHIPADU COUNTER - KURUNGAZHIPU DEVASWOM - PARAVUR GROUP- SUO MOTU PROCEEDINGS INITIATED - REG.) PETITIONER(S):

-------------------------- THE TRAVANCORE DEVASWOM BOARD, REPRESENTED BY ITS EXECUTIVE ENGINEER, THIRUNAKKARA, KOTTAYAM DIVISION.

BY ADV. SRI.M.V.S.NAMBOOTHIRI, SC, TDB RESPONDENT(S):

---------------------------- THE DEPUTY DIRECTOR, LOCAL FUND AUDIT, THIRUVANANTHAPURAM.

BY ADV.A.RENJITH, SR. GOVERNMENT PLEADER BY P.RAMACHANDRAN, AMICUS CURIAE FOR OMBUDSMAN THIS DEVASWOM BOARD PETITION HAVING COME UP FOR ADMISSION ON 19-08-2015, THE COURT ON THE SAME DAY PASSED THE FOLLOWING:

THOTTATHIL B.RADHAKRISHNAN & SUNIL THOMAS, JJ.

.................................................................... DBP No.90 of 2015 .................................................................... Dated this the 19th day of August, 2015.

O R D E R

Thottathil B.Radhakrishnan, J.

Perused the application along with the materials. We accept the report of the learned Ombudsman and grant sanction as prayed for, in terms of the recommendation of the learned Ombudsman. The work shall be completed at the earliest. The expenditure shall be subjected to audit. This DBP is ordered accordingly. (THOTTATHIL B.RADHAKRISHNAN, JUDGE) (SUNIL THOMAS, JUDGE) jg