Travancore Devaswom Board v. Deputy Director
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT:
THE HONOURABLE MR.JUSTICE THOTTATHIL B.RADHAKRISHNAN & THE HONOURABLE MRS. JUSTICE ANU SIVARAMAN WEDNESDAY, THE 2ND DAY OF DECEMBER 2015/11TH AGRAHAYANA, 1937 DBP.No. 127 of 2015 () ----------------------- PETITIONER(S):
-------------- TRAVANCORE DEVASWOM BOARD, REPRESENTED BY ITS EXECUTIVE ENGINEER, MAVELIKKARA.
BY ADV. SRI.D.SREEKUMAR, SC, TDB RESPONDENT(S):
-------------- THE DEPUTY DIRECTOR, LOCAL FUND ACCOUNT, THIRUVANANTHAPURAM.
BY GOVERNMENT PLEADER SRI.A.RANJITH.
THIS DEVASWOM BOARD PETITION HAVING BEEN FINALLY HEARD ON 02-12-2015, THE COURT ON THE SAME DAY PASSED THE FOLLOWING:
THOTTATHIL B.RADHAKRISHNAN & ANU SIVARAMAN, JJ.
----------------------------------------------- D.B.P.No.127 of 2015 ----------------------------------------------- Dated this the 2nd December, 2015
O R D E R
Thottathil B.Radhakrishnan, J.
We have perused the report of the learned Ombudsman for Travancore Devaswom Board and Cochin Devaswom Board and the application along with the documents placed therewith. We accept the recommendations of the learned Ombudsman and record that the Temple Advisory Committee will contribute 50% of the estimated expenditure. With that, we approve the request and grant permission as sought for, in terms of the recommendation of the learned Ombudsman. The work shall be completed at the earliest and the expenditure shall be subjected to audit after the work is completed.
The D.B.P is ordered accordingly.
THOTTATHIL B.RADHAKRISHNAN JUDGE ANU SIVARAMAN JUDGE vgs4/12