IN THE HIGH COURT OF KERALA AT ERNAKULAM

PRESENT:

THE HONOURABLE MR.JUSTICE THOTTATHIL B.RADHAKRISHNAN & THE HONOURABLE MRS. JUSTICE ANU SIVARAMAN WEDNESDAY, THE 25TH DAY OF NOVEMBER 2015/4TH AGRAHAYANA, 1937 DBP.No. 135 of 2015 () -----------------------

IN THE MATTER OF TBD REPORT NO.160/2015

PETITIONER:

------------- TRAVANCORE DEVASWOM BOARD REPRESENTED BY ITS EXECUTIVE ENGINEER, THIRUNAKKARA KOTTAYAM DIVISION.

BY ADV. SRI.M.V.S.NAMBOOTHIRI, SC, TRAVANCORE DEVASWOM BOARD RESPONDENTS:

----------------- THE DEPUTY DIRECTOR, KERALA STATE AUDIT DEPARTMENT THIRUVANANTHAPURAM BY SENIOR GOVERNMENT PLEADER SRI.A.RENJITH THIS DEVASWOM BOARD PETITION HAVING COME UP FOR ADMISSION ON 25-11-2015, THE COURT ON THE SAME DAY PASSED THE FOLLOWING:

THOTTATHIL B.RADHAKRISHNAN & ANU SIVARAMAN, JJ.

= = = = = = = = = = = = = = = = = = D.B.P. No.135 of 2015 = = = = = = = = = = = = = = = = = = Dated this the 25th day of November, 2015

O R D E R

Thottathil B.Radhakrishnan, J.

1. Perused the application and the materials produced therewith. We have also seen the report of the learned Ombudsman for Travancore and Cochin Devaswom Boards. We are satisfied that the application is only to be allowed in the light of what has been reported by the learned Ombudsman.

2. In the result, this application is allowed, in terms of the report of the learned Ombudsman. The work shall be completed at the earliest and the expenditure incurred shall be subjected to audit upon completion of the work.

DBP ordered accordingly.

Thottathil B.Radhakrishnan, Judge Anu Sivaraman, Judge sj26/11