Travancore Devaswom Board v. Deputy Director, Lfa, Tvm
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT:
THE HONOURABLE MR.JUSTICE THOTTATHIL B.RADHAKRISHNAN & THE HONOURABLE MRS. JUSTICE ANU SIVARAMAN WEDNESDAY, THE 23RD DAY OF DECEMBER 2015/2ND POUSHA, 1937 DBP.No. 142 of 2015 () ----------------------------------------- PETITIONER(S):
----------------------- TRAVANCORE DEVASWOM BOARD, REPRESENTED BY ITS EXECUTIVE ENGINEER, SABARIMALA DEVELOPMENT PROJECT PAMPA.
BY ADV. SRI.KRISHNA MENON, SC, TRAVANCORE DEVASWOM BOARD RESPONDENT(S):
---------------------------- THE DEPUTY DIRECTOR, LOCAL FUND AUDIT, THIRUVANANTAPURAM.
R BY SRI.A.RENJITH, GOVERNMENT PLEADER THIS DEVASWOM BOARD PETITION HAVING BEEN FINALLY HEARD ON 23-12-2015, THE COURT ON THE SAME DAY PASSED THE FOLLOWING: DG
THOTTATHIL B.RADHAKRISHNAN & ANU SIVARAMAN, JJ.
------------------------------------------------------------------ D.B.P.No.142 of 2015 ------------------------------------------------------------------- Dated this the 23rd day of December, 2015
O R D E R
Thottathil B.Radhakrishnan, J.
Perused materials along with the application and the report of the learned Ombudsman. We concur with the views of the learned Ombudsman and grant permission as sought for in terms of the recommendation of the learned Ombudsman. The work will be commenced immediately following the current Makaravilakku season. It shall be ensured that the work is done with requisite performance guarantee and the officers of the Board will ensure that quality is maintained. Expenditure incurred for the work shall be subjected to audit after the work is completed. DBP ordered accordingly.
Sd/- (THOTTATHIL B.RADHAKRISHNAN, JUDGE) Sd/- (ANU SIVARAMAN, JUDGE) //TRUE COPY// P.A TO JUDGE DG