Karthiayani v. The Secretary, Kerala State Electricity Board
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT:
THE HONOURABLE MR. JUSTICE A.MUHAMED MUSTAQUE MONDAY, THE 31ST DAY OF AUGUST 2015/9TH BHADRA, 1937 OP(C).No. 2090 of 2015 (O) ------------------------------------ CC 4/2008 OF INDUSTRIAL TRIBUNAL, PALAKKAD ........
PETITIONER(S)/APPLICANT:
----------------------------------------- KARTHIAYANI, AGED 81 YEARS, W/O.KRISHNANKUTTY, MYTHRI NAGAR, PIRAYIRI, PALAKKAD.
BY ADV. SMT.M.CHANDRALEKHA RESPONDENT(S)/OPPOSITE PARTIES:
-------------------------------------------------------
1. SECRETARY, KERALA STATE ELECTRICITY BOARD, VYDHYUTHI BHAVAN, PATTOM, THIRUVANANTHAPURAM-695 004.
2. THE EXECUTIVE ENGINEER, ELECTRICAL DIVISION, KERALA STATE ELECTRICITY BOARD, PALAKKAD - 678 014.
3. THE ASSISTANT EXECUTIVE ENGINEER, ELECTRICAL SUB-DIVISION, SULTHAN PLT, PALAKKAD -678 014.
4. THE ASSISTANT ENGINEER, ELECTRICAL SECTION, MELAMURI, PALAKKAD -678 307.
5. SRI. S.G.DEVASSY, PETTY CONTRACTOR, GOPURATHINGAL HOUSE, ANGAMALY SOUTH P.O., ERNAKULAM DISTRICT - 683 573.
6. THE INDUSTRIAL TRIBUNAL, PALAKKAD (THE COMMISSIONER FOR WORKMEN'S COMPENSATION), PALAKKAD.
R1 TP R4 BY ADV. SRI.SAJEEVKUMAR K.GOPAL,SC R6 BY GOVERNMENT PLEADER SRI.BIJU MEENATTOOR THIS OP (CIVIL) HAVING COME UP FOR ADMISSION ON 31-08-2015, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING: msv/
OP(C).No. 2090 of 2015 (O) ------------------------------------- APPENDIX PETITIONER(S)' EXHIBITS ------------------------------------- P1 - TRUE COPY OF THE ORDER IN W.C.C.4/2008 OF THE WORKMEN'S COMPENSATION PALAKKAD.
P2 - A TRUE COPY OF THE APPLICATION DATED 5.9.2011. P3 -A TRUE COPY OF THE APPLICATION SUBMITTED BY THE PETITIONER BEFORE THE COMMISSIONER FOR WORKMEN'S COMPENSATION PALAKKAD ON 29.9.2014 FOR RECOVERY OF BALANCE AMOUNT.
P4 - A TRUE COPY OF THE APPLICATION DATED 5.6.2015 BEFORE THE 6TH RESPONDENT INDUSTRIAL TRIBUNAL, PALAKKAD. RESPONDENT(S)' EXHIBITS:
----------------------------------------- NIL //TRUE COPY// P.S.TO JUDGE.
Msv/
A.MUHAMED MUSTAQUE, J.
------------------------------------- O.P.(C)No.2090 of 2015 ---------------------------------- Dated this the 31st day of August, 2015.
J U D G M E N T
The applicant in W.C.C.No.4/08 on the file of the Commissioner for Workmen's Compensation, Palakkad, has approached this Court for a speedy disposal of Ext.P4.
2. Ext.P4 is an application calculating the amount due to the petitioner based on the award passed on W.C.C.No.4/08. It appears that there are some disputes regarding the amount payable to the applicant. The learned Standing counsel for the respondent submitted that they have deposited the entire amount. The petitioner submits that the petitioner has not received the entire amount as affirmed by the respondent.
In view of the facts of the case, there shall be a direction to the 6th respondent, who is the Commissioner for Workmen's Compensation, Palakkad, to dispose Ext.P4 within a period of 4 months of receipt of copy of this
O.P.(C)No.2090 of 2015 judgment, after hearing both the petitioner and the respondents.
Sd/- A.MUHAMED MUSTAQUE, Judge.
ami/ //True copy// P.A.to Judge