Kerala State Rural Roads Development Agency v. G.V.Davis

2015-10-16Honourable Mr. Justice A.Muhamed Mustaque3 pages

IN THE HIGH COURT OF KERALA AT ERNAKULAM

PRESENT:

THE HONOURABLE MR. JUSTICE A.MUHAMED MUSTAQUE FRIDAY, THE 16TH DAY OF OCTOBER 2015/24TH ASWINA, 1937 RP.No. 191 of 2015 ---------------------------- JUDGMENT DATED 20-12-2014 IN WP(C) 32889/2014 .........

REVIEW PETITIONER(S)/RESPONDENTS 1 AND 2 IN W.P.(C): -------------------------------------------------------------------------------------

1. KERALA STATE RURAL ROADS DEVELOPMENT AGENCY, TC 28/885, 3RD FLOOR, CSI BUILDING, PULIMOODU, THIRUVANANTHAPURAM-695 001, REPRESENTED BY ITS SUPERINTENDING ENGINEER.

2. SUPERINTENDING ENGINEER, KERALA STATE RURAL ROADS DEVELOPMENT AGENCY, TC 28/885, 3RD FLOOR, CSI BUILDING, PULIMOODU, THIRUVANANTHAPURAM-695 001.

BY GOVERNMENT PLEADER SMT.C.K.SHERIN RESPONDENT(S)/PETITIONER & 3RD RESPONDENT IN WP(C): -----------------------------------------------------------------------------------------

1. G.V.DAVIS, S/O.G.O. VARGHESE, CONTRACTOR, GOPURATHINGAL HOUSE, KARUKUTTY P.O., ANGAMALY VIA, ERNAKULAM DISTRICT.

2. FRANCIS, S/O.ELUVATHINGAL CHAKKUNNY, CHEVOOR DESOM, THRISSUR TALUK, THRISSUR DISTRICT, PIN - 680 001. BY ADVS. SRI.BABU JOSEPH KURUVATHAZHA SRI.P.T.ABHILASH THIS REVIEW PETITION HAVING COME UP FOR ADMISSION ON 16-10-2015, THE COURT ON THE SAME DAY PASSED THE FOLLOWING: msv/

A.MUHAMED MUSTAQUE, J.

------------------------------------------ R.P.No. 191 of 2015 in W.P(C).No.32889 of 2014 ------------------------------------------- Dated this the 16th October, 2015

O R D E R

The review is at the instance of the Government. The writ petitioner approached this Court in the Writ Petition to release the bill amount for the work undertaken for effecting improvements to three roads. It was opposed by the learned Government Pleader that there was a Vigilance Enquiry initiated. This Court directed to release the amount and issue completion certificate without prejudice to the right to pursue the vigilance enquiry.

2. The review is in fact necessitated when the Director of Vigilance and Anti Corruption Bureau as per communication dated 8.1.2015 found that the petitioner caused damage to the tune of 10,64,177/- as loss to the ₹ exchequer, and therefore, the judgment is required to be reviewed. It is submitted that the Government is entitled to withhold the payment. It is further submitted that

RP.191/15 subsequently, based on further verification, the amount has been reduced to 77,830/-. It is also submitted that ₹ the Government is examining the entire matter threadbare and require some more time to complete the enquiry. It is further submitted that if the amount is released, it will prejudice the Government as well as recovery of the amount.

3. This Court is of the view that the Government shall complete the enquiry within three months from the date of receipt of a copy of this judgment. The respondent shall release the amount after deducting 11,00,000/-. The ₹ release of this amount would depend upon the outcome of the Vigilance enquiry. The balance amount shall be released within two weeks. it is made clear that the amount need be released only in accordance with the agreement.

The Review Petition is disposed of as above.

A.MUHAMED MUSTAQUE JUDGE vgs19/10/15