IN THE HIGH COURT OF KERALA AT ERNAKULAM

PRESENT:

THE HONOURABLE MR.JUSTICE V.CHITAMBARESH FRIDAY, THE 27TH DAY OF FEBRUARY 2015/8TH PHALGUNA, 1936 WP(C).No. 5715 of 2015 (L) --------------------------- PETITIONER:

------------------ THE MUNNAR SERVICE CO-OP. BANK LTD., MUNNAR, IDUKKI DISTRICT, REPRESENTED BY ITS SECRETARY.

BY ADV. SRI.LATHEESH SEBASTIAN RESPONDENTS:

-----------------------

1. KANNAN DEVAN HILLS PLANTATION CO. PVT. LTD., KDHP HOUSE, MUNNAR, IDUKKI DISTRICT, REPRESENTED BY ITS GENERAL MANAGER 685 586.

2. THE SENIOR MANAGER-ENGINEERING, ENGINEERING DEPARTMENT, KANNAN DEVAN HILLS PLANTATION CO.PVT.LTD., KDHP HOUSE, MUNNAR, IDUKKI DISTRICT 685 586.

THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON 27-02-2015, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:

WP(C).No. 5715 of 2015 (L) APPENDIX PETITIONER(S)' EXHIBITS EXT. P1 :

TRUE COPY OF THE LAND TAX RECEIPT DT.25-3-14. EXT. P2 :

TRUE COPY OF THE OWNERSHIP CERTIFICATE DT.4-1-2012. EXT. P3 :

TRUE COPY OF THE ELECTRICITY BILL DT.13-1-15. EXT. P4 :

TRUE COPY OF THE REQUEST OF THE PETITIONER DT.18-12-14. EXT. P5 :

TRUE COPY OF THE LETTER OF R2 DT.3-2-15.

RESPONDENT(S)' EXHIBITS : NIL /TRUE COPY/ P.A. TO JUDGE.

V. CHITAMBARESH, J -------------------------------- WP(C) NO. 5715 OF 2015 ------------------------------------ Dated this the 27th day of February, 2015

JUDGMENT

The order of status quo in Writ Appeal Nos. 227, 224 and 574 of 2001 does not disable a single phase connection to be altered into a three phase electricity connection. So is the case with regard to the order of status quo passed in SLP (C) Nos. 5049, 506 and 5067 of 2007 when the petitioner admittedly enjoys a single phase connection.

2.

The respondents are hence directed to provide three phase electricity connection to the petitioner in the place of the existing single phase connection. This is however subject to the technical feasibility in regard to the building wherein three phase electricity connection is sought. The needful shall be done within a period of one month from the date production of a copy of this judgment.

The Writ Petition is disposed of.

V. CHITAMBARESH JUDGE ncd