Unnikannan v. The Secretary
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT:
THE HONOURABLE MR.JUSTICE V.CHITAMBARESH FRIDAY, THE 27TH DAY OF MARCH 2015/6TH CHAITHRA, 1937 WP(C).No. 9974 of 2015 (V) ------------------------------------- PETITIONER:
-------------------------- UNNIKANNAN S/O. NADARAJAN, DWARAKA, AMBAZHA VAYAL PERINAD P.O., KOLLAM BY ADV. SRI.O.D.SIVADAS RESPONDENTS:
---------------------------- 1.
THE SECRETARY REGIONAL TRANSPORT AUTHORITY, KOLLAM - 691 001 2.
ARVINDAN, VASANTHALAYAM THAMARAKULAM, KOLLAM - 691 001 BY GOVERNMENT PLEADER SRI. R. RANJITH THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON 27-03-2015, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
WP(C).No. 9974 of 2015 (V) APPENDIX PETITIONER(S)' EXHIBITS ------------------------------------- EXHIBIT-P1- COPY OF THE TIME SHEET ALLOTTED TO THE PETITIONER'S SERVICE EXHIBIT-P2- COPY OF THE TIME SHEET ALLOTED TO THE 2ND RESPONDENT'S SERVICE EXHIBIT-P3- COPY OF THE REQUEST SUBMITTED BY THE PETITIONER DATED 22.12.2014 RESPONDENT(S)' EXHIBITS:-NIL --------------------------------------- /TRUE COPY/ P.A. TO JUDGE
V. CHITAMBARESH, J --------------------------------------- W.P.(C). NO. 9974 OF 2015 ---------------------------------------- Dated this the 27th day of March, 2015
JUDGMENT
The petitioner contends that the anomaly if any in the settlement of timings has to be rectified. Ext. P3 request has accordingly been filed pointing out the anomaly between Exts. P1 and P2 time sheets.
2.
I direct the first respondent to consider Ext. P3 request with notice to the petitioner and the second respondent. The needful shall be done within a period of two months from the date of production of a copy of this judgment. The writ petition is disposed of.
V. CHITAMBARESH JUDGE