The Secretary, A.K.G Memorial Labour Contract Society Ltd v. The Executive Engineer,
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT:
THE HONOURABLE MR. JUSTICE A.MUHAMED MUSTAQUE WEDNESDAY, THE 4TH DAY OF NOVEMBER 2015/13TH KARTHIKA, 1937 WP(C).No. 13299 of 2014 (J) ---------------------------- PETITIONER:
------------------ THE SECRETARY, A.K.G MEMORIAL LABOUR CONTRACT SOCIETY LTD., P.B.NO.15, 145/16B, FORT ROAD, THALASSERY - 670 001.
BY ADVS.SRI.K.MOHANAKANNAN SMT.A.R.PRAVITHA SMT.D.S.THUSHARA SRI.H.PRAVEEN (KOTTARAKARA) RESPONDENT(S):
-------------------------
1. THE EXECUTIVE ENGINEER, PAZHASSI IRRIGATION PROJECT, DIVISION NO.II, KANNUR - 670 001.
2. THE CHIEF ENGINEER, PAZHASSI IRRIGATION PROJECT, KAVERI HOUSE, WEST HILL P.O., KOZHIKODE - 678 001.
BY GOVERNMENT PLEADER SMT.C.K.SHERIN THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON 04-11-2015, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
mbr/
WP(C).No. 13299 of 2014 (J) --------------------------------------- APPENDIX PETITIONERS' EXHIBITS:
EXT. P1 :
TRUE COPY OF THE AGREEMENT NO.EE-3/2013-14 DATED 5.7.2013. EXT. P2 :
TRUE COPY OF THE AGREEMENT DATED 31.3.2014.
EXT. P3 :
TRUE COPY OF THE REPRESENTATION DATED 19.4.2014 SUBMITTED BEFORE THE 1ST RESPONDENT.
RESPONDENTS' EXHIBITS:
NIL.
//TRUE COPY// P.S. TO JUDGE mbr/
A.MUHAMED MUSTAQUE, J.
***************************************************************************** W.P.(C) No.13299 of 2014 ****************************************************************************** Dated this the 4th day of November, 2015
JUDGMENT
In the light of the interim order dated 10.6.2014, any amount payable to the petitioner remains in arrears shall be paid within a period of two months from the date of receipt of a copy of this judgment.
The writ petition is disposed of as above.
Sd/- A.MUHAMED MUSTAQUE, JUDGE ln