High Court of KeralaWP(C)/22036/2015disposed of

M/S Sowparnika Projects And Infra Structure Pvt Ltd v. Assistant Engineer

2015-07-22Honourable Mr.Justice V.Chitambaresh3 pages

IN THE HIGH COURT OF KERALA AT ERNAKULAM

PRESENT:

THE HONOURABLE MR.JUSTICE V.CHITAMBARESH WEDNESDAY, THE 22ND DAY OF JULY 2015/31ST ASHADHA, 1937 WP(C).No. 22036 of 2015 (D) ---------------------------- PETITIONER(S):

-------------------------- M/S SOWPARNIKA PROJECTS AND INFRA STRUCTURE PVT LTD. A-26 KOWDIAR GARDENS, KOWDIAAR P.O., THIRUVANANTHAPURAM 695 003 REPRESENTED BY ITS DIRECTOR MEENAKSHI RAMJI, AGED 44 YEARS, W/O. SUBRAMANIAM RAMJI, 204, SAIRAGH APARTMENTS, A BLOCK, AECS LYT, KUNDALAHALLY, BANGALORE 560 037. BY ADVS.SRI.MANSOOR.B.H.

SRI.K.JAYAPRASAD RESPONDENTS:

------------------------- 1.

ASSISTANT ENGINEER KERALA STATE ELECTRICITY BOARD LTD., POOJAPURA SECTION THIRUVANANTHAPURAM 695 001.

2.

DEPUTY CHIEF ENGINEER KERALA STATE ELECTRICITY BOARD LTD., THIRUVANANTHAPURAM 695 001.

3.

CORPORATION OF THIRUVANANTHAPURAM CORPORATION OFFICE, THIRUVANANTHAPURAM REPRESENTED BY ITS SECRETARY 695 001.

BY SRI. N. NANDAKUMARA MENON, SC, TVPM CORPORATION BY SRI.P.K.MANOJKUMAR,SC,TVPM CORPORATION BY SRI. SAJEEV KUMAR K GOPAL, SC, KSEB BY SRI.JAICE JACOB,SC,KERALA STATE ELECTRICITY BOARD THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON 22-07-2015, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:

WP(C) NO. 22036/2015 APPENDIX PETITIONER(S) EXHIBITS EXHIBIT P1 :

TRUE COPY OF THE BUILDING PERMIT BEARING NUMBER E6/BA-C124/2009 ISSUED BY THE THIRD RESPONDENT EXHIBIT P2 :

TRUE COPY OF THE RECEIPT DATED 1709.2014 BEARING NUMBER 123133 ISSUED BY THE THIRUVANANTHAM CORPORATION. EXHIBIT P3 :

TRUE COPY OF THE APPLICATION DATED 09.06.2015 SUBMITTED BY THE PETITIONER BEFORE THE SECOND RESPONDENT RESPONDENT(S) EXHIBITS : NIL /TRUE COPY/ P.A. TO JUDGE.

V. CHITAMBARESH, J -------------------------------- WP(C) NO. 22036 OF 2015 ------------------------------------ Dated this the 22nd day of July, 2015

JUDGMENT

Ext.P1 building permit has expired. The petitioner has applied for its renewal. Ext.P2 is the acknowledgment for the alleged renewal application.

2.

The petitioner was provided with a temporary connection for construction. The petitioner apprehends disconnection of electricity supply. This is on the basis that the construction permit has not been renewed. Ext.P3 representation has been filed by the petitioner. The same is pending consideration with the second respondent. 3.

I direct the second respondent to consider Ext.P3 representation with notice to the petitioner as well as the third respondent. The needful shall be done within a period of two months from the date of receipt of a copy of this judgment. The electricity supply (temporary connection) to the petitioner shall not be snapped in the meanwhile. The Writ Petition is disposed of.

V. CHITAMBARESH JUDGE ncd