IN THE HIGH COURT OF KERALA AT ERNAKULAM

PRESENT:

THE HONOURABLE MR. JUSTICE A.V.RAMAKRISHNA PILLAI WEDNESDAY, THE 5TH DAY OF AUGUST 2015/14TH SRAVANA, 1937 WP(C).No. 23655 of 2015 (F) ---------------------------- PETITIONER :

----------------------- SAFEER.P.A., PANDARA ARAKKAL HOUSE, WEST KODUR, KODUR, MALAPPURAM.

BY ADV. SRI.K.V.GOPINATHAN NAIR RESPONDENT :

-------------------------- THE SECRETARY, REGIONAL TRANSPORT AUTHORITY, MALAPPURAM- 676 505.

BY GOVERNMENT PLEADER SMT. K.A.SANJEETHA THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON 05-08-2015, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:

sts

WP(C).No. 23655 of 2015 (F) ----------------------------------------- APPENDIX PETITIONER(S)' EXHIBITS ------------------------------------- EXHIBIT P1.

COPY OF THE APPLICATION SUBMITTED BY THE PETITIONER BEFORE THE RESPONDENT DATED 5.2.15.

EXHIBIT P2.

COPY OF THE JUDGMENT OF THIS HONOURABLE COURT IN WPC NO.6275/15 DATED 2.3.15.

EXHIBIT P3.

COPY OF THE JUDGMENT OF THIS HONOURABLE COURT IN WPC.NO. 2844/13 DATED 21.11.14.

EXHIBIT P4.

COPY OF THE REPRESENTATION SUBMITTED BY THE PETITIONER BEFORE THE RESPONDENT DATED 27.7.15.

RESPONDENT(S)' EXHIBITS:

NIL ------------------------------------------ /TRUE COPY/ P.A.TO JUDGE sts

A.V. RAMAKRISHNA PILLAI, J.

------------------------------------- W.P.(C) No.23655 of 2015 -------------------------------------- Dated this the 5th day of August, 2015.

JUDGMENT

The petitioner is seeking for a direction to the respondent to consider Ext.P4 representation submitted by the petitioner in the next timing conference of the respondent scheduled to be held on 10.8.2015.

2.

The petitioner is conducting stage carriage with a set of timing issued in the year 2001. The petitioner alleges that when a vacant timing arose, the petitioner filed Ext.P1. By Ext.P2, this Court directed the respondent to consider Ext.P1 clarifying that the revision if made shall also be subject to any further revision made under D3 circular. The petitioner further alleges that D3 circular is not so far implemented and in the light of Ext.P3 judgment, the same is not possible for implementation. Pointing out the above judgment, the petitioner filed Ext.P4 representation for the consideration of the respondent. Now timing conference is scheduled to be

W.P.(C) No.23655 of 2015 -2held on 10.8.2015. In the said timing conference if Ext.P3 and p4 is not taken into consideration, the petitioner would put to irreparable injury and hardship. It is with this background, the petitioner has come up before this court.

3.

I have heard the learned counsel for the petitioner and the learned Government Pleader in the matter. Considering the nature of the submissions and the nature of the relief sought for, the writ petition is disposed of directing the respondent to consider and pass appropriate orders on Ext. P4 in the next timing conference scheduled to be held on 10.8.2015 itself without fail.

Sd/- A.V. RAMAKRISHNA PILLAI JUDGE Scl.