K Sugathan v. The Superintending Engineer
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT:
THE HONOURABLE MR. JUSTICE A.MUHAMED MUSTAQUE MONDAY, THE 26TH DAY OF OCTOBER 2015/4TH KARTHIKA, 1937 WP(C).No. 29444 of 2015 (E) ---------------------------- PETITIONER :
--------------------- K. SUGATHAN PWD CONTRACTOR, KIZHAKKUMMURY P.O., KAKKODY, CALICUT-673 611.
BY ADVS.SRI.PHILIP J.VETTICKATTU SRI.B.PREMNATH RESPONDENT(S) :
----------------------------
1. THE SUPERINTENDING ENGINEER PUBLIC WORKS DEPARTMENT, (ROADS AND BRIDGES) NORTH CIRCLE, CALICUT-673 001.
2. DEPUTY SUPERINTENDING ENGINEER PUBLIC WORKS DEPARTMENT, (ROADS AND BRIDGES) NORTH CIRCLE, CALICUT-673 001.
3. ASSISTANT EXECUTIVE ENGINEER PWD ROADS SUB DIVISION, KOZHIKODE-673 004.
4. EXECUTIVE ENGINEER PWD ROADS SUB DIVISION, KOZHIKODE-673 020.
R1 TO R4 BY GOVT. PLEADER SMT. C.K. SHERIN THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON 26-10-2015, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
Mn ...2/-
WP(C).No. 29444 of 2015 (E) ---------------------------------------- APPENDIX PETITIONERS' EXHIBITS :
------------------------------------- EXT. P1 :
COPY OF THE RELEVANT PAGES OF AGREEMENT DTD.30.7.2008 BETWEEN THE PETITIONER AND THE 3RD RESPONDENT. EXT. P2 :
COPY OF THE RELEVANT PAGES OF THE AGREEMENT DTD.15.6.2009 BETWEEN THE PETITIONER AND THE 3RD RESPONDENT. EXT. P3 :
COPY OF THE REQUEST MADE BY THE PETITIONER BEFORE THE 3RD RESPONDENT.
EXT. P4 :
COPY OF THE REPRESENTATION FILED BY THE PETITIONER ON 1.4.2015 BEFOFE THE 3RD RESPONDENT.
RESPONDENT(S)' EXHIBITS : NIL ----------------------------------------------------------- //TRUE COPY// P.A. TO JUDGE Mn
A.MUHAMED MUSTAQUE, J.
- - - - - - - - - - - - - - - - - - - - - - - - - - W.P.(C) No. 29444 of 2015 - - - - - - - - - - - - - - - - - - - - - - - - - - Dated this the 26th day of October, 2015
JUDGMENT
Petitioner has undertaken certain work on behalf of the respondent referred in the writ petition. Petitioner approaches this Court on account of non preparation of final bill. Petitioner made Ext.P4 request before the 3rd respondent to prepare the final bill.
2. Considering the facts and circumstances of the case, there shall be direction to the 3rd respondent to prepare final bill within two months. The petitioner shall produce a copy of the writ petition along with a copy of this judgment before the 3rd respondent for compliance. This writ petition is disposed of accordingly. Sd/- A.MUHAMED MUSTAQUE JUDGE sm/