IN THE HIGH COURT OF KERALA AT ERNAKULAM

PRESENT:

THE HONOURABLE MR.JUSTICE V.CHITAMBARESH TUESDAY, THE 29TH DAY OF SEPTEMBER 2015/7TH ASWINA, 1937 WP(C).No. 29504 of 2015 (K) ---------------------------- PETITIONER(S):

-------------------------- THE SOUTH INDIAN BANK LTD REP. BY THE MANAGER THRIKKAKKARA BRANCH PIPE LINE JUNCTION, THRIKKAKKARA, COCHIN-682 021.

BY ADVS.SRI.K.T.THOMAS (KANNAMPALLIL) SRI.D.SREENATH SRI.G.KIRAN RESPONDENT(S):

---------------------------- 1.

THE DEPUTY CHIEF LABOUR COMMISSIONER(CENTRAL) KENDRIYA SHRAM SADAN, OLIMUGHAL, KAKKANAD, COCHIN - 682 030 2.

LABOUR ENFORCEMENT OFFICER(CENTRAL) KENDRIYA SHRAM SADAN, OLIMUGHAL, KAKKANAD, COCHIN - 682 030 3.

MS.SUBAIDA M.S KALAPURACKAL HOUSE OPPOSITE Y.M.C.A THRIKKAKKARA, COCHIN-682 021.

BY ADV.K.A.SANJEETHA, GOVERNMENT PLEADER THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON 29-09-2015, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:

WP(C).No. 29504 of 2015 APPENDIX PETITIONERS EXHIBITS P1- TRUE COPY OF THE RELEVANT PORTION OF THE PROCEEDINGS OF THE ASST.LABOUR COMMISSIONER DATED 14.11.2014 P2- TRUE COPY OF THE PETITION FILED BY THE THIRD RESPONDENT BEFORE THE SECOND RESPONDENT DATED 24.11.2014 P3- TRUE COPY OF THE LETTER ISSUED BY THE 2ND RESPONDENT TO THE PETITIONER DATED 8.12.2014 P4- TRUE COPY OF THE REPLY FILED BY THE PETITIONER DATED 23.12.2014 P5-TRUE COPY OF THE COMMUNICATION OF RETRENCHMENT DATED 26.3.2015 P6-TRUE COPY OF THE COMMUNICATION ISSUED BY THE SECOND RESPONDENT DATED 6.5.2015 P7-TRUE COPY OF THE REPLY FILED BY THE PETITIONER DATED 25.5.2015 P8-TRUE COPY OF THE INSPECTION REPORT ISSUED BY THE SECOND RESPONDENT DATED 14.8.2015 P9-TRUE COPY OF THE REPLY FILED BY THE PETITIONER DATED 19.9.2015. RESPONDENTS EXHIBITS NIL TRUE COPY SKS P.A. TO JUDGE

V.CHITAMBARESH, J.

--------------------- W.P (C) No.29504 of 2015 --------------------- Dated this the 29th day of September, 2015

J U D G M E N T

The petitioner has filed Ext.P9 reply to Ext.P8 inspection report on the question of payment of bonus to the 3rd respondent. 2.

I direct the 1st respondent to consider Ext.P9 reply to Ext.P8 report with notice to the petitioner and the 3rd respondent. The needful shall be done within a period of one month from the date of receipt of a copy of this judgment.

The Writ Petition is disposed of accordingly. V.CHITAMBARESH, Judge.