High Court of KeralaWP(C)/32555/2014disposed of

V.Santhosh Gnanadas v. The Manager, Engineering Department K.D.H.P Co (P) Ltd

2015-03-03Honourable Mr.Justice V.Chitambaresh3 pages

IN THE HIGH COURT OF KERALA AT ERNAKULAM

PRESENT:

THE HONOURABLE MR.JUSTICE V.CHITAMBARESH TUESDAY, THE 3RD DAY OF MARCH 2015/12TH PHALGUNA, 1936 WP(C).No. 32555 of 2014 (T) ---------------------------- PETITIONER:

------------------ V.SANTHOSH GNANADAS, TRADE LINKS, NO. 7 MAIN ROAD, MUNNAR PIN 685 612 BY ADV. SRI.BABU PAUL RESPONDENTS:

------------------------

1. THE MANAGER, ENGINEERING DEPARTMENT K.D.H.P CO (P) LTD., MUNNAR P.O, 685 612.

2. THE SANCTION HOLDER/SUPPLY OF ELECTRICITY MUNNAR VALLEY, ZONAL MANAGER, K.D.H.P CO.PVT LTD MUNNAR P.O 685 612.

THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON 03-03-2015, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:

WP(C).No. 32555 of 2014 (T) APPENDIX PETITIONER(S)' EXHIBITS EXT.P1 TRUE COPY OF THE RECEIPT DATED 23/5/2014 EXT.P2 TRUE COPY OF THE REQUEST DATED 9/1/2014 BY THE PETITIONER EXT.P3 TRUE COPY OF THE REPLY DATED 31/1/2014 BY THE RESPONDENTS EXT.P4 THE TRUE COPY OF THE JUDGMENT DATED 12/9/2013 IN WPC NO 22705/2013 RESPONDENT(S)' EXHIBITS : NIL /TRUE COPY/ P.A. TO JUDGE.

V. CHITAMBARESH, J -------------------------------- WP(C) NO. 32555 OF 2014 ------------------------------------ Dated this the 3rd day of March, 2015

JUDGMENT

The order of status quo passed in other litigation does not disable the upgradation of the electric connection enjoyed by the petitioner hitherto. The issue is covered by Ext.P4 judgment of this court dated 12.09.2013 in WP(C) No. 22705/2013. 2.

The respondents are therefore directed to upgrade the power connection of the petitioner from single phase to three phase subject to technical feasibility. The needful shall be done within a period of one month from today.

The Writ Petition is disposed of.

V. CHITAMBARESH JUDGE ncd