M/S. Flow Tech Engineers And Suppliers v. Kerala Water Authority
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT:
THE HONOURABLE MR. JUSTICE A.MUHAMED MUSTAQUE FRIDAY, THE 13TH DAY OF NOVEMBER 2015/22ND KARTHIKA, 1937 WP(C).No. 34379 of 2015 (V) ------------------------------------------- PETITIONER(S) :
------------------------- M/S.FLOW TECH ENGINEERS AND SUPPLIERS, KADUVIAL P.O., VALLIKKUNNAM, ALAPPUZHA- 690 501, REPRESENTED BY ITS PROPRIETOR, BANERJI, VETTATHETHU HOUSE, KADUVINAL P.O., VALLIKKUNNAM, ALAPPUZHA- 690 501.
BY ADV. SMT.K.N.RAJANI RESPONDENT(S) :
----------------------------
1. KERALA WATER AUTHORITY, REPRESENTED BY ITS MANAGING DIRECTOR, JAL BHAVAN, THIRUVANANTHAPURAM- 695 001.
2. SUPERINTENDING ENGINEER, KERALA WATER AUTHORITY, PUBLIC HEALTH CIRCLE, MOOVATTUPUZHA, PIN- 686 661.
3. EXECUTIVE ENGINEER, KERALA WATER AUTHORITY, PUBLIC HEALTH DIVISION, ALUVA- 683 101.
BY ADV. SRI.MILLU DANDAPANI, S.C, KERALA WATER AUTHORITY BY ADV. SRI.GEORGE MATHEW, S.C, KERALA WATER AUTHORITY THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON 13-11-2015, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
Msd.
WP(C).No. 34379 of 2015 (V) ------------------------------------------- APPENDIX PETITIONER(S)' EXHIBITS :
----------------------------------------- EXHIBIT P1: TRUE COPY OF THE JUDGMENT IN W.P.(C).NO.16788/2015 DATED 09.06.2015.
EXHIBIT P2: TRUE COPY OF THE REPRESENTATION OF THE PETITIONER DATED 12.10.2015.
EXHIBIT P3: TRUE COPY OF THE REPRESENTATION OF THE PETITIONER DATED 02.11.2015.
RESPONDENT(S)' EXHIBITS :
------------------------------------------- NIL //TRUE COPY// P.S.TO JUDGE.
Msd.
A.MUHAMED MUSTAQUE, J.
---------------------------------------- W.P(C)No. 34379 of 2015 ---------------------------------------- Dated this the 13th day of November, 2015
J U D G M E N T
Petitioner approached the first respondent/the Kerala Water Authority represented by its Managing Director for extension of time to complete the work undertaken by him. Exts.P2 and P3 are the requests.
2. This Court is of the view, there shall be a direction to the first respondent to consider Exts.P2 and P3 and pass appropriate orders within a period of one month from the date of receipt of a copy of this judgment, after hearing the petitioner. Till a decision is taken by the first respondent on Exts.P2 and P3, the work awarded to the petitioner shall not be terminated.
This writ petition is disposed of as above.
A.MUHAMED MUSTAQUE, MBS/ Judge
WP(C).NO.
:-2-: