← Library
High Court of KeralaWP(C)/35545/2015disposed of

Bechi Krishna K.G v. Pavithreswaram Grama Panchayath

2015-11-244 pages

IN THE HIGH COURT OF KERALA AT ERNAKULAM

PRESENT:

THE HONOURABLE MR.JUSTICE K.HARILAL TUESDAY, THE 24TH DAY OF NOVEMBER 2015/3RD AGRAHAYANA, 1937 WP(C).No. 35545 of 2015 (P) ---------------------------- PETITIONER(S):

-------------------------- BECHI KRISHNA K.G., PROPRIETOR, MALAYIL INDANE SERVICES, DWARAKA, MARANADU, PAVITHRESHWARAM, KOTTARAKKARA, KOLLAM.

BY ADVS.SRI.GEORGE VARGHESE(PERUMPALLIKUTTIYIL), SRI.A.R.DILEEP, SRI.MANU SEBASTIAN, SRI.P.J.JOE PAUL.

RESPONDENT(S):

----------------------------

1. PAVITHRESHWARAM GRAMA PANCHAYATH, REPRESENTED BY ITS SECRETARY, KARIMPUZHA P.O., KOTTARAKKARA, KOLLAM DISTRICT-679 513.

2. SECRETARY, PAVITHRESHWARAM GRAMA PANCHAYATH, KARIMPUZHA P.O., KOTTARAKKARA, KOLLAM DISTRICT-679 513.

THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON 24-11-2015, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:

rs.

WP(C).No. 35545 of 2015 (P) APPENDIX PETITIONER'S EXHIBITS:- EXT.P1 COPY OF THE LETTER DATED 06/11/2014 FROM INDIAN OIL CORPORATION TO THE PETITIONER.

EXT.P2 COPY OF THE LEASE DEED NO.1596/15 OF KOTTARAKKARA SRO.

EXT.P3 COPY OF THE LEASE DEED NO.1706/15 OF KOTTARAKKARA SRO.

EXT.P4 COPY OF THE APPLICATION FOR BUILDING PERMIT DATED 22/07/2015 SUBMITTED BY THE PETITIONER BEFORE THE 2ND RESPONDENT.

EXT.P5 COPY OF THE LETTER DATED 22/09/2015 FROM PETROLEUM AND EXPLOSIVES SAFETY ORGANIZATION, MINISTRY OF COMMERCE AND INDUSTRY, GOVERNMENT OF INDIA.

RESPONDENT'S EXHIBITS:- NIL.

//TRUE COPY// P.S. TO JUDGE rs.

K.HARILAL, J.

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ W.P.(C) No.35545 of 2015 _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ Dated this the 24th day of November, 2015.

JUDGMENT

The petitioner is a widow, who has been granted LPG Distributorship by the Indian Oil Corporation. For the purpose of commissioning the Distributorship, the petitioner has to construct an LPG godown. Therefore, according to the petitioner, she has taken property on lease by Exts.P2 & P3 and made Ext.P4 application, seeking building permit for the construction of the godown, before the 2nd respondent. But, the 2nd respondent has not considered Ext.P4 application. This is the grievance projected in this writ petition.

2. Heard the learned counsel for the petitioner, who confined his argument to a direction to the 2nd respondent to consider and pass order on Ext.P4 application seeking for building permit for the

WP(C).35545/15 :2: construction of the LPG godown for distribution.

3. Having regard to the above submission, the 2nd respondent is directed to consider and pass order on Ext.P4 application, at the earliest, at any rate, within two months from the date of receipt of a copy of this judgment.

This writ petition is disposed of.

Sd/- K. HARILAL, JUDGE okb.