Orissa Collieries v. Govt.Of India And ORS
IN THE HIGH COURT OF ORISSA AT CUTTACK
W.P.(C). No. 22527 of 2011 Orissa Collieries Labour Union and others ....
Petitioners Mr. Gopal Krushna Mohanty, Advocate -versusUnion of India and others ....
Opposite Parties Mr. Jateswar Nayak, CGC
CORAM:
THE CHIEF JUSTICE JUSTICE R. K. PATTANAIK Order No.
ORDER
06.04.2022 03.
1. Learned counsel appearing for the Petitioners is not able to explain to the Court what the precise grievance of the Petitioners is except saying that the existing 'Check off System' for verification of membership of the Petitioner No.1 union should continue.
2. As far as the Court can see, the communication dated 18th May, 2011 of the Ministry of Labour & Employment Government of India in fact allows such system to continue. Consequently, it is not clear what the grievance of the Petitioners is.
3. The writ petition is accordingly dismissed. The interim order passed earlier, stands vacated.
4. The Superintendent of the concerned Branch to immediately communicate this order to the concerned authority. (Dr. S. Muralidhar) Chief Justice (R. K. Pattanaik) Judge S. Behera