Orissa High CourtSTREV/357/2008dismissed
State v. Hindustan Steel Work
2022-04-19Dr. Justice S. Muralidhar (Cj),Mr. Justice R.K.Pattanaik1 pages
IN THE HIGH COURT OF ORISSA AT CUTTACK
STREV No.357 of 2008 State of Orissa represented through the Commissioner of Sales Tax, Orissa, Cuttack ....
Petitioner Mr. S.S. Padhy, A.S.C.
-versusM/s. Hindustan Steel Works Construction Ltd., Bolani, Keonjhar ....
Opposite Party
CORAM:
THE CHIEF JUSTICE JUSTICE R. K. PATTANAIK
ORDER
19.04.2022 Order No.
03.
Misc. Case No.118 of 2008 and STREV No.357 of 2008
1. There is an inordinate delay of 1914 days in filing the revision petition. The delay is not properly explained.
2. Accordingly, the Misc. Case for condonation of delay is dismissed. Consequently, the STREV is dismissed. (Dr. S. Muralidhar) Chief Justice (R. K. Pattanaik) Judge S.K. Guin