IN THE HIGH COURT OF ORISSA AT CUTTACK

W.P (C) No. 8805 of 2014 UBV Infrastructure Limited .....

Petitioner Ms. S. Jena, Adv.

Vs.

Executive Engineer, Lower Suktel Dam Division, Magurbeda and others .....

Opposite parties Addl. Government Advocate

CORAM:

DR. JUSTICE B.R. SARANGI MR. JUSTICE V. NARASINGH

ORDER

22.02.2022 Order No.

04.

This matter is taken up through hybrid mode.

2.

Since the period of tender, i.e., for the year 2010-11 has already been over, by efflux of time, the writ petition has become infructuous.

3.

Ms. S. Jena, learned counsel for the petitioner states that the petitioner is entitled to get refund of some amount in terms of the agreement. If that be so, liberty is granted to the petitioner to approach the appropriate forum in accordance with law. 4.

With the aforesaid liberty, the writ petition stands disposed of.

Ashok (DR. B.R. SARANGI) JUDGE (V. NARASINGH) JUDGE