M/S.Sagar Construction,Cuttack v. Ee,Govt Of Odisha,Cuttack
IN THE HIGH COURT OF ORISSA AT CUTTACK
W.P.(C) No. 3634 of 2016 M/s. Sagar Consruction, Cuttack .....
Petitioner Mr. B.N. Mohanty, Advocate Vs.
Executive Engineer & Anr..
.....
Opposite parties State Counsel
CORAM:
DR. JUSTICE B.R. SARANGI MR. JUSTICE V. NARASINGH
ORDER
16.02.2022 Order No.
This matter is taken up through hybrid mode.
2.
Heard learned counsel for the petitioner.
3.
Since the contract period of the work has been over since long, this Court is not inclined to entertain this writ petition. However, liberty is granted to the petitioner to pursue his remedy before the appropriate forum as per the terms of the agreement itself.
4.
Interim order passed earlier stands vacated.
5.
With the above observation, the writ petition stands disposed of.
Alok ...........................
(DR. B.R. SARANGI) JUDGE .....................................
(V. NARASINGH) JUDGE