Sharad Ku.Gupta v. Prasanna Ku.Sahu
IN THE HIGH COURT OF ORISSA AT CUTTACK
CONTC NO.67 OF 2018 Sharad Kumar Gupta ....
Petitioner Mr. Biplaba P.B.Bahali, Advocate.
-versusPrasanna Kumar Sahu, Executive Engineer, Rural Works Division, Sambalpur and others ....
Opp.parties Mr. A.K. Nanda, Addl. Govt. Advocate
CORAM:
JUSTICE JASWANT SINGH JUSTICE M.S.SAHOO Order No.
ORDER
09.02.2022 02.
1. This matter is taken up through hybrid mode.
2. The petitioner in the contempt petition alleges noncompliance of the order dated 17.02.2017 passed in W.P.(C) No.2551 of 2017, wherein, the petitioner, who is a Super Class Contractor prayed for a direction to reimburse and pay the differential amount claimed by the petitioner, said to have been paid towards minimum wages of labour, from 06.10.2012 till June,2014 along with price escalation bill.
3. By order dated 17.02.2017, this Court disposed of the writ petition with the following directions:
" ... ... Considering the submissions made and without expressing any opinion on the merits of the case, this writ petition is disposed of directing the Executive Engineer, Rural Works Division, Sambalpur (opposite party no.3), to take effective steps to consider and dispose of the representation of the petitioner dated 24.01.2017, as per Annexure-5 series to the writ petition, if the same is still pending, as expeditiously as possible, preferably within a period of two months from the of receipt of certified copy of
// 2 // this order, keeping in view the judgment of this Court passed in W.P.(C) No.29272 of 2011.
Writ petition is accordingly disposed of."
4. It is revealed from the present petition filed by the petitioner that for compliance of the aforesaid order, by letter no.867 dated 08.03.2017 (Annexure-2 series) the opposite party-Engineer requested the petitioner to furnish the documents as per the modalities framed by the Government, to consider the payment of enhanced wages. The documents that was to be produced by the petitioner/Contractor, as indicated in the said letter are as follows:
"i) Labour Registration Certificate.
ii) Wages Register in support of minimum wages for verification and record.
iii) Other relevant records/Registers/ document."
5.
It is submitted by the learned counsel for the petitioner that the petitioner by letter dated 11.03.2017 (Annexure-3 series) has replied to the letter of the opposite party no.1-Executive Engineer, Rural Works Division, Sambalpur, inter alia stating that the Labour Registration Certificate is not required to be produced now and the Registers as requested to be produced have not been preserved or are not required to be preserved after four years, as the date of completion of work is 04.05.2014.
6. From the aforesaid letter of the petitioner, it is apparent that though he has filed the writ petition on
// 3 // 10.02.2017, he opted not to preserve the records based on which the claim in the writ petition, i.e., W.P.(C) No.2551 of 2017 was to be substantiated.
7. In view of the aforesaid facts, it cannot be held that there is any violation of this Court's order dated 17.02.2017 as alleged by the petitioner. Moreover, the requirement of the Labour Registration Certificate, Wages Register in support of payment of minimum wages and any other relevant records/ Registers/documents as requested by the opposite party-authority is relevant and germane consideration before reimbursing the claim of the petitioner regarding payment of the wages which should have been received by the labourers/workers, who worked under the contractor.
8. In view of the aforesaid discussions, the present petition is dropped, there being no violation of the order dated 17.02.2017 passed in W.P.(C) No.2551 of 2017.
(Jaswant Singh) (M.S. Sahoo) Judge Judge February 9th 2022 Cuttack Gs/Radha