IN THE HIGH COURT OF ORISSA AT CUTTACK

W.P.(C) No. 24576 of 2012 The Executive Engineer, Sambalpur Irrigation Division ....

Petitioner Mr. P.K. Muduli, AGA -versusGanesh Sarangi and another ....

Opposite Parties None

CORAM:

THE CHIEF JUSTICE JUSTICE R. K. PATTANAIK Order No.

ORDER

01.08.2022 05.

1. No notice has been served on Opposite Party No.1 in all these years. The Court does not propose to order fresh notice at this stage considering the nature of the matter.

2. Consequently, leaving the questions of law arising from the impugned order open for decision in some other appropriate case, the present petition is disposed of.

3. The interim order passed earlier stands vacated. (Dr. S. Muralidhar) Chief Justice (R. K. Pattanaik) Judge S. Behera