28.07.2022 Order No.
01.
This matter is taken up through hybrid mode.
2.
Heard Mr. B.K. Biswal, learned counsel for the Petitioner. 3.
The Petitioner has filed this Writ Petition seeking to quash the decision of the Opposite Party No.2 vide Annexure-5 debarring the Petitioner for three years from further bidding in OMC. 4.
In course of hearing, learned counsel for the Petitioner states that highlighting the grievances, the Petitioner has made a representation to Opposite Party No.2 vide Annexure-9 and the same may be directed to be considered within a stipulated time. 5.
Considering the contentions raised by learned Counsel for the Petitioner, this Court, without expressing any opinion on the merits of the case, disposes of the writ Petition directing opposite party No.2 to consider the representation filed by the Petitioner vide Annexure-9, and pass appropriate order in accordance with law
within a period of six weeks from the date of production of certified copy this order.
6.
Issue urgent certified copy as per rules Arun/Banita (DR. B.R. SARANGI) JUDGE (S.K. MISHRA) JUDGE