Orissa High CourtSTREV/46/2013dismissed
State v. M/S.Gitashree Indust
2022-07-06Dr. Justice S. Muralidhar (Cj),Mr. Justice R.K.Pattanaik1 pages
IN THE HIGH COURT OF ORISSA AT CUTTACK
STREV No.46 of 2013 State of Odisha ....
Petitioner Mr. S.K. Pradhan, ASC -versusM/s. Gitashree Industries ....
Opposite Party
CORAM:
THE CHIEF JUSTICE JUSTICE R. K. PATTANAIK
ORDER
06.07.2022 STREV No.46 of 2013 & M.C. No.134 of 2013 04.
Delay of more than 300 not having been properly explained, the Order No.
Court is not inclined to condone the delay. The revision petition is accordingly dismissed. The question of law however left upon to the consideration some other appropriate case. (Dr. S. Muralidhar) Chief Justice (R. K. Pattanaik) Judge TUDU