← Library
Orissa High CourtWP(C)/15303/2018disposed off

M/S.Jay Bharat Construction v. Gm,South Eastern Railway

2022-06-27Dr. Justice B.R.Sarangi,Mr. Justice Sanjay Kumar Mishra1 pages

IN THE HIGH COURT OF ORISSA AT CUTTACK

W.P.(C) No. 15303 of 2018 M/s. Jay Bharat Construction .....

Petitioner Mr. D.K. Dwibedi, Advocate Vs.

General Manager, South Eastern Railway and Ors.

.....

Opposite Parties State Counsel

CORAM:

DR. JUSTICE B.R. SARANGI Mr. JUSTICE S. K. MISHRA

ORDER

27.06.2022 Order No.

02.

This matter is taken up through hybrid mode.

2.

Learned counsel for the Petitioner stated that by efflux of time, the Writ Petition has become infructuous. 3.

In view of the above submission, this Writ Petition stands disposed of as infructuous.

...........................

(DR. B.R. SARANGI) JUDGE .....................................

(S. K. MISHRA) Alok/Ananta JUDGE