IN THE HIGH COURT OF ORISSA AT CUTTACK

STREV No. 14 of 2015 M/s. Sourav Industries ....

Petitioner Mr. U.C. Behura, Advocate -versusState of Odisha and Others ....

Opposite Parties Mr. S.K. Pradhan, Addl. Standing Counsel

CORAM:

THE CHIEF JUSTICE JUSTICE M.S. RAMAN

ORDER

06.12.2022 Order No.

Misc. Case No.99 of 2018 07.

1. There is delay of 146 days in filing the present revision petition.

2. The reasons set out in the application are neither convincing nor reasonable and, accordingly, the Court is not inclined to condone the delay. The application is dismissed.

STREV No. 14 of 2015

3. Consequently, the revision petition is dismissed. Nevertheless, the question urged is left open for decision in any other appropriate case. (Dr. S. Muralidhar) Chief Justice (M.S.Raman) Judge S.K. Jena/Secy.