Niranjan Nayak v. Special Land Acquisition Officer, Keonjhar
IN THE HIGH COURT OF ORISSA AT CUTTACK
W.P.(C) No.33990 of 2021 Niranjan Nayak ....
Petitioner Mr. S.P. Das, Advocate -versusSpecial Land Acquisition Officer-cum-Competent Authority, N.H.-215, Keonjhar & another ....
Opposite parties Ms. M.M. Mohanty, Advocate for O.P. No.1
CORAM:
JUSTICE BISWAJIT MOHANTY JUSTICE K.R.MOHAPATRA Order No.
ORDER
08.02.2022 01.
1.
This matter is taken up by video conferencing mode. 2.
Heard Mr. S.P. Das, learned counsel for the petitioner and Ms. M.M. Mohanty, learned counsel representing National Highways Authority of India.
3.
At the outset, on the oral prayer of Mr. Das, learned counsel for the petitioners, he is permitted to implead Regional Director, National Highways Authority of India at 3rd Floor, Pal Heights, Jayadev Vihar, Bhubaneswar as opposite party No.3.
Office is directed to make consequential corrections in the cause title. 4.
According to Mr. Das the petitioner is aggrieved by inaction of the authorities in releasing the compensation amount determined by the competent authority under Section 3-G of the National Highways Act, 1956 in respect of left out structure on Plot No 204/973 under Khata No. 156/227 in the village Ramchandrapur in the district of
// 2 // Keonjhar within a stipulated period.
5.
It is found from the counter affidavit filed on behalf of the Special Land Acquisition Officer-cum-Competent Authority that the case for sanction and placement of funds towards compensation for left-out structure in respect of village Ramchandrapur under Ghasipura Tahasil has already been recommended to the Project Director N.H.A.I vide letter dated 1.6.2018 under Annexure-E/1. Ms. Mohanty submits that since sanction has not been made by the Regional Director, National Highways Authority of India, Bhubaneswar (opposite party No.3) the amount has not yet been released in favour of the petitioners. 6.
During course of hearing, Mr. Das submits that liberty may be granted to the petitioner to file a representation before the Regional Director, National Highways Authority of India, Bhubaneswar (opposite party No.3) in the matter and the said opposite party be directed to take a decision on such motion at an early date. 7.
Considering the submissions made and without expressing any opinion on the merits of the case, this Court grants liberty to the petitioner to file a representation before opposite party No.3 through registered post within a period of two weeks from today. In the event, such a representation is filed along with a certified copy of this order, the opposite party No.3 is directed to take a decision on the same in accordance with law within a period of three months from the date of receipt of such representation. If it is found that the petitioner is entitled to the compensation as claimed, the same shall be released to him forthwith within a period of four weeks from the date of taking such decision.
// 3 // 8.
Accordingly, the writ petition is disposed of. 9.
Issue urgent certified copy as per rules.
amit (Biswajit Mohanty) Judge (K.R.Mohapatra) Judge